PROJECT DETAILS
RTC Project No. 212073
RTC Project Manager (PM)
Kimberly Diegle, P.E..
(775) 335-1844
kdiegle@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Nichols Consulting Engineers
Construction Contractor: Sierra Nevada Construction
PROJECT DESCRIPTION
Roadway reconstruction of Arrowcreek Parkway from South Virginia Street to 250 feet south of Rubblestone Drive and rehabilitation on Zolezzi Lane from Arrowcreek Parkway to Jeppson Lane. Construction work will include removal and replacement of the roadway structural section, sidewalk and curb and gutter replacement as necessary, reconstruction of existing curb ramps as necessary, traffic signal improvements, and other incidentals necessary for the reconstruction of the street segment within the project limits.
LATEST NEWS
Construction began June 12, 2023, and is anticipated to be complete in mid-September 2023. An additional left turn lane has been included in the project at eastbound Arrowcreek Parkway to northbound South Virginia Street. Visit the Weekly Traffic Control Report for updates on closures in the area.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Completed
Final Design: Summer 2022 to Spring 2023
Construction: June 2023 – September 2023
FINANCIAL INFORMATION
Total Project Estimate: $4,284,546
Funding Source: RTC Fuel Tax
Post updated on: October 5, 2023
Arrowcreek Parkway Project Map