PCC PREVENTATIVE MAINTENANCE

Status: Upcoming Projects

Total Project Cost: 1,500,000

PROJECT DETAILS
RTC Project No. 0243021

RTC Project Manager (PM)
Scott Gibson

RTC Engineering Department
(775) 348-0171

Design Firm: Lumos & Associates, Inc.

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project is to develop a preventive maintenance program for the Portland Cement Concrete Pavements in the region. Concrete is a small part of the road network and includes a few streets and select intersections. Proposed work includes joint sealing, spall repairs and panel replacements.

LATEST NEWS
The design consultant Lumos and Associates, Inc., is currently scoping these pavements for cost and prioritization.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: January 2026
Final Design: January 2026
Construction: March 2026

FINANCIAL INFORMATION
Total Project Estimate: $1,500,000
Funding Source: RTC Fuel Tax

Post updated on: December 30, 2025