PROJECT DETAILS
RTC Project No. 0215008
RTC Project Manager (PM)
Jeff Wilbrecht, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: CA Group, Inc.
Construction Contractor: to be determined
PROJECT DESCRIPTION
The project scope includes design and construction improvements along the following Intersections:
1. South Virginia Street at Kietzke Lane
2. Double R Boulevard and Amston Road
3. McCarran Boulevard and Mira Loma Drive
4. Veterans Parkway and Cesena Avenue / Pesaro Way
5. Mae Anne Avenue and Ambassador Drive and Stone Valley Drive
LATEST NEWS
CA Group, Inc. was selected for design and construction management. Agreement awarded during the RTC Board Meeting in December 2024.
30% Design plans are anticipated by April 2025. Construction is expected to start in Spring 2026.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2025
Final Design: Fall 2025
Construction: Spring 2026
FINANCIAL INFORMATION
Total Project Estimate: $ 1,250,000.00
Funding Source: RTC Fuel Tax
Post updated on: January 27, 2025