April 12, 2024


1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Project is nearing completion but there will be some temporary traffic controls in place over the next two weeks to address final cleanup and punch list items.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction work is weather dependent.

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction is complete. Minor punch item list work and landscape maintenance taking place (weather permitting).

Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):

  • Major construction completed.
  • Intermittent one lane closures.
  • Weather dependent items: landscape, permanent striping, and punch list items.

Phase 3 – east of US 395 Ramps to Sutro Street (Reno):

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Lane closures. One lane in each direction.
  • Upcoming roadwork and paving between Sutro Street and 9th Street:
    • Intermittent Sutro/Oddie (half intersection closures). Detours will be posted.
    • One way for each direction along Oddie.
      • North side closure: April 8th – 23rd
      • South side closure: April 24nd – May 6th

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com


SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

April 2nd – May 3rd

  • One-way eastbound-only traffic will be allowed on Selmi Drive at all times (24/7). Detours are provided for westbound traffic thru McCarran Boulevard.

May 6th – May 26th

  • One-way westbound-only traffic will be allowed on Selmi Drive at all times (24/7). Detours are provided for eastbound traffic thru McCarran Boulevard.
  • Access will remain open for businesses and residential.

STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844

Construction is underway and will continue through the end of May 2024.

Roadway removal and paving operations begin Monday, April 15th

  • East Freeport Way and Snider Way will be intermittently closed to through traffic at Stanford Way while paving is completed.
  • One-way southbound-only traffic will be allowed on Stanford Way and will remain in place for the duration of construction. Detours are provided for northbound traffic.
  • Freeport Way will be closed to through traffic at Stanford Way while work on the west side of the street continues.
  • On-street parking will not be allowed on Stanford Way for the duration of construction 24/7. While individual driveway closures may occur, access will be maintained to all businesses during construction.

PYRAMID WAY AND NORTH MCCARRAN BOULEVARD FIBER CONNECTIVITY
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

This project is substantially complete.  Occasional shoulder closures may occur on McCarran Boulevard between Sullivan Lane and Rock Boulevard for final work items.


TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Moana Lane and Baker Lane/Smith Drive (Reno)

Occasional shoulder and lane closures may occur on Moana Lane. Major work at the Moana Lane and Baker Lane intersection will resume in May for final traffic signal installation tasks.

Prater Way and 4th Street (Sparks)

The following traffic controls will be in place until the end of April at the intersection of Prater Way and 4th Street for traffic signal replacement:

  • A temporary all-way stop will be in effect at the intersection.
  • Various lane and shoulder closures.
  • All turning movements and driveways will remain open.

Delays are possible and motorists should consider an alternate route until the work is complete.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Construction is underway and will continue through June. Motorists can expect the following traffic controls:

Baring Boulevard between Sparks Boulevard and Vista Boulevard

  • Various left lane closures for fiber optic installation.
  • Lane closures (if needed) will occur Monday thru Friday, 9:00 a.m. – 3:00 p.m. daily.
  • All driveways and turning movements will remain open.

Vista Boulevard between Baring boulevard and Los Altos Parkway (south)

  • Various shoulder closures for fiber optic installation.
  • All driveways and turning movements will remain open.

STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. Traffic will be shifted to the center of Steamboat Parkway upon completion of median island removal between Veterans Parkway and Marketplace Drive.

April 15th – April 19th

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Intermittent should closure on Veterans Parkway southbound from the intersection of Veterans Parkway/Steamboat Parkway to 1,150 feet north of intersection.