2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
There is no work scheduled for the week of August 19-23.
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Las Brisas Boulevard between Brittania Drive and McCarran Boulevard
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
Los Altos Parkway between North Vista Boulevard and Goodwin Road
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
August 19 – August 23
- Crews will begin at Mae Anne and progress to Del Webb Parkway with lowering utilities in preparation of the mill and full operation to follow.
- Traffic impacts will be minimal with minor delays in specific locations with flagger control.
- This activity will last 3-4 weeks.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- NV Energy crews on site removing northbound power poles by Carpeteria.
- Crews working on the southbound side removing/installing new driveways, sidewalk, and pedestrian ramps.
- Night work starting the week of August11, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.
- West Coast Dirt Works crews will be on-site doing private development work during the weekends of August 16-19 and 23-26. Work to include sewer line connection along northbound lanes closer to the intersection at Patriot Boulevard.
SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work is substantially complete. Motorists may see occasional lane and shoulder closures for final work items.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024.
August 19 – August 23
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Steamboat Parkway will be reduced to one lane in each direction at times.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
August 19 – August 23
- One travel lane in each direction will be maintained on E 2nd Street for shoulder work.
- A detour will be in place for eastbound traffic on E 2nd Street as crews construct trench through roudabout. Detour will be as follows:
- Road will be closed in eastbound direction at the intersection of Pringle Way and E 2nd Street.
- Eastbound traffic will be detoured back to Kietzke Lane via Manuel Street and Kuenzli Street.
SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Work is substantially complete. Motorists may see occasional lane and shoulder closures for final work items.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
August 17
Clear Acre Lane and N. McCarran Boulevard
- Paving work will begin on the north leg of the intersection on Clear Acre Lane between Selmi Drive and N. McCarran Boulevard in the hours between 4:00 a.m. – 9:00 a.m.
- Motorists should expect lane restrictions in the southbound direction during this time.
Los Altos Parkway and Galleria Parkway
- Paving work will take place near the intersection.
- Motorists should expect lane closures in the westbound direction during daytime working hours.
August 19 – August 23
El Rancho Drive and G Street
- Motorists should anticipate daytime shoulder and intermittent lane closures near the signalized intersection while crews complete trenching activities.
- At least one lane for each travel direction will remain open throughout this phase of work.