August 9, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Pavement Striping 7:00 p.m. – 7:00 a.m.

  • Various project street from August 11-15

Pavement Markings 7:00 p.m. – 7: a.m.

  • Wild Island Court, from Lincoln Way to the end – August 12-13


LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

Las Brisas Boulevard between Brittania Drive and McCarran Boulevard

  • Work is substantially complete.
  • Contractor will be on site to complete minor work items throughout July.
  • Two-way traffic anticipated to be maintained.

Los Altos Parkway between North Vista Boulevard and Goodwin Road

  • Work is substantially complete.
  • Contractor will be on site to complete minor work items throughout July.
  • Two-way traffic anticipated to be maintained.


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

August 12 – August 16

  • Crews will begin at Mae Anne and progress to Del Webb Parkway with lowering utilities in preparation of the mill and full operation to follow.
  • Traffic impacts will be minimal with minor delays in specific locations with flagger control.
  • This activity will last 3-4 weeks.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
  • Night work is anticipated in August, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Work is substantially complete. Motorists may see occasional lane and shoulder closures for final work items.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024.

August 12 – August 16

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Steamboat Parkway will be reduced to one lane in each direction at times.
  • Shoulder closure for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.


SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Work is substantially complete. Motorists may see occasional lane and shoulder closures for final work items.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Construction begins August 5 on Yorkshire Drive and Carlyle Drive.
  • Single lane closures and local traffic only.
  • Limited on-street parking.


NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 3351865

August 12 – August 16

  • Motorists may see occasional lane and shoulder closures for final work items.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

August 12- August 16

El Rancho Drive and G Street

  • Motorists should anticipate daytime shoulder and intermittent lane closures near the signalized intersection while crews complete trenching activities.
  • At least one lane for each travel direction will remain open throughout this phase of work.

Los Altos Parkway and Galleria Parkway

  • Crews will begin work to extend the westbound to southbound left turn pocket at the intersection.
  • Motorists should expect lane closures in the westbound direction during daytime working hours.