July 19, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Micro-Surfacing

STREETFROMTODATE
Stead BoulevardSilver Lake RoadEcho Avenue07/22-23
Vista BoulevardBrierly WayWingfield Hills Drive07/23-27
Sullivan LanePrater WayRancho Boulevard07/24-26

Pavement Striping 7:00 p.m. – 7:00 a.m.

STREETFROMTODATE
Stead BoulevardSilver Lake RoadEcho Avenue07/22-23
Vista BoulevardBrierly WayWingfield Hills Drive07/23-27
Sullivan LanePrater WayEl Rancho Boulevard07/24-26

Pavement Markings (Thermoplastic)

STREETFROMTODATE
Ferrari McLeod BoulevardGardella AvenueParr Boulevard07/22
Bennie LaneGardella AvenueParr Boulevard07/22
Timber WayValley RoadSutro Street07/22-23
Tampa StreetTimber WayTimber Way07/22-23
Bravo StreetMount McClellan StreetAlbert Way07/22-24
Echo CourtEcho AvenueNorth Cud-de-sac07/22-24
Mount Charleston StreetStead BoulevardEcho Avenue07/22-24
Wingfield Parkway Vista BoulevardWingfield Springs Road07/23
Stead BoulevardSilver Lake RoadEcho Avenue07/24-26

Micro Mill

STREETFROMTODATE
Veterans ParkwayS Meadows ParkwayGeiger Grade Road07/22-23


LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

Las Brisas Boulevard between Brittania Drive and McCarran Boulevard

Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.

Los Altos Parkway between North Vista Boulevard and Goodwin Road

Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Project is substantially completed. Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
  • Construction during the day. Concrete work (sidewalk, curb, and gutter, driveways, etc.) along the northbound side of South Virginia.
  • Night work is anticipated in August, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.


SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

Project is substantially completed. Intermittent lane shifts for punch item list work and landscape work.


TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Work is substantially complete at the Moana Lane/ Baker Lane, and Prater Way/ 4th Street intersections. Motorists may see occasional shoulder and lane closures for final work items.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Motorists may see various lane and shoulder closures at the following locations for fiber optics installation:

  • Galleria Parkway between Los Altos Parkway and Disc Drive
  • Los Altos Parkway between Galleria Parkway and Ion Drive


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024.

July 22 – July 26

  • Two travel lanes in each direction will be maintained on Steamboat Parkway. Steamboat Parkway will be reduced to one lane in each direction at times.
  • Shoulder closure for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.


SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

No active traffic control for this project.


NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 3351865

June 15 to July 24

  • One-way traffic on North Virginia Street for north bound traffic only.
  • Utilize Sierra Street for business access and alternate route.
  • No on-street parking.

July 25 to August 2

  • Two-way traffic on North Virginia Street with one lane in each direction
  • No on-street parking


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

Work will begin on the project on July 22 at the following project locations:

El Rancho Drive and G Street

  • Motorists should anticipate daytime shoulder and isolated lane closures near the signalized intersection beginning Monday, July 22.
  • At least one lane for each travel direction will remain open throughout this phase of work.