June 27, 2025

2025 PREVENTATIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Micro-surfacing

STREET FROMTODATE
Zolezzi Lane Arrow Creek Parkway SE Side of Circle06/23-24
Lakeside DriveHuffaker LaneN. Side of Park Gate06/25
Delucchi LaneS. Virginia Street Home Gardens Drive06/26
Hammill LaneKietzke LaneCul-de-Sac06/26
Neil LaneMeadowood Mall CircleNeil Road06/26

Pavement Marking (Night Work 7:00 p.m. – 7:00 a.m.)

STREETFROMTODATE
S Rock BoulevardGlendale AvenueBridge06/22
Zolezzi LaneArrow Creek Parkway SE Side of Circle06/23-24
Lakeside DriveHuffakerN. Side of Park Gate06/25
Delucchi LaneS. Virginia Street Home Hardens Dirve06/26
Hammill LaneKietzke LaneEnd of Culd-de-Sac06/26
Neil laneMeadowood Mall CircleNeil Road06/26

Pavement Marking

STREETFROMTODATE
Coney Island DriveGreg Parkway Dead End06/23
Greg Parkway Coney Island DirveGreg Street 06/23
Dunn Circle Glendale AvenueWatson Way 06/23
S Rock BoulevardGlendale Avenue Bridge06/23-24
Zolezzi LaneArrow Creek Parkway SE Side of Circle06/27


ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865

Arlington Avenue will be closed between West 1st Street and Island Avenue. Northbound traffic will be detoured to the Virginia Street bridge or Center Street. Southbound traffic and pedestrians will be detoured to the Sierra Street bridge.

  • West Street will be open to westbound traffic only between West Street and Stevenson Street.
  • Wingfield Park will remain closed from May 5, 2025, until summer 2026.
  • River recreation detours will also be in place.
  • View detour maps at ArlingtonBridges.com


MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844

Continuous single lane closures on Mill Street westbound from Greg Street/Terminal Way to the I-580 southbound ramp intersection. Daytime and nighttime construction with single lane closures on Mill Street between I-580 and Terminal Way.

Bus Stop Closures:

  • The Route 12/14 westbound bus stop at Mill Street/Matley Lane is closed
  • The Route 14 eastbound bus stop at Mill Street Gould Street is closed.

Riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.

Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

June 23 – June 27

General lane restrictions in all directions to perform landscaping.


VETERANS PARWAY ITS-LONG MEADOW DRIVE TO STEAMBOAT PARKWAY
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Intermittent single lane closures on southbound Veterans Parkway between Long Meadow Drive and Steamboat Parkway for traffic fiber installations.


TRAFFIC SIGNAL MODIFICATION 24-01
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861

June 2025

No traffic control anticipated on this project in early June.


MEADOWOOD MALL REHABILITATION
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

June 23 – June 27

Roadway and sidewalk reconstruction to be performed on Meadowood Mall Circle between S. Virginia Street and Meadowood Mall Circle, Meadowood Mall Way between S. Virginia Street and Meadowood Mall Circle, and Neil Way between Neil Road and Meadowood Mall Circle.

Meadowood Mall Circle

  • One lane each direction will be maintained during the day.
  • Route 1 Bus Stop on Meadowood Mall Circle (at Jiffy Lube) will be temporarily closed.
  • Jiffy Lube driveway access will be maintained at all times.
  • Directional roadway closures in effect during nighttime working hours.

Neil Way

  • One lane each direction will be maintained during the day.
  • Directional roadway closures in effect.

Meadowood Mall Way

  • One lane each direction will be maintained during the day.
  • Directional roadway closures in effect during nighttime working hours.


VISTA PRATER SIGNAL FIBER CONNECTION PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Installation of traffic fiber network on Prater Way from Sparks Boulevard to Vista Boulevard and Vista Boulevard from Prater Way to Kleppe Lane.

June 23 – June 27

Prater Way

  • Shoulder closures eastbound and westbound directions.
  • Intermittent lane restrictions and lane reductions through intersections.

Vista Boulevard

  • Shoulder closures northbound and southbound directions.
  • Intermittent lane restrictions and lane reductions through intersections.


TRAFFIC SIGNAL FIBER 25-01
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Installation of traffic fiber on Vista Boulevard from Prater Way to Baring Boulevard, Longley Lane from Maestro Drive to S. McCarran Boulevard, Kietzke Lane from Fisherman’s Park to Galletti Way, and Galletti Way from Kietzke Lane to Glendale Avenue.

Vista Boulevard

Single lane closures for potholing and trenching operations.

Longley Lane

Single lane closures for potholing and trenching operations.


VISTA AND DISC INTERSECTION IMPROVEMENT PROJECT
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Major road work at the Vista Boulevard and Disc Drive intersection in Sparks is expected to begin in July. In the meantime, the following work associated with the project at other locations is underway:

Mira Loma Drive /Veterans Parkway in Reno:

  • Closure of the eastbound Mira Loma right turn lane to Veterans Parkway for crosswalk safety improvements. This closure is 24/7 until the project is completed. Motorists can still make the right turn using the thru lane.
  • Periodic closures of the right lane on Veterans Parkway southbound at the intersection. Veterans Parkway Lane closures will only occur between 8:00 a.m. – 4:00 p.m., Monday through Friday.
  • The multi-use pathway along Veterans Parkways will be closed intermittently during work to ensure the safety of users and construction crews.

Nichols Drive in Sparks:

  • Various shoulder closures in both directions east of McCarran Boulevard for median island reconstruction.

2025 BRIDGE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

June 23 -June 27

Ralston Street Bridge over I-80 will be closed June 24 – July 2. Alternate routes are Sierra Street or Virginia Street Bridges to the South and Washington and Vine Street Bridges to the North.