2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Pavement Patching
STREET | FROM | TO | DATE |
Woodland Avenue | Sugar Pine Court | Fourth Street | 7/2 |
Sugar Pine Court | Cul-de-sac | Woodland Avenue | 7/2 |
Sullivan Lane | Prater Way | Rancho Boulevard | 7/2-3 |
Micro-Surfacing
STREET | FROM | TO | DATE |
Evans Avenue | Second Street | Jodi Drive | 7/1 |
Stoker Avenue | Fourth Street | Seventh Street | 7/2 |
Summit Ridge Interchange | Summit Ridge | McCarran ROW Fence | 7/2 |
Timber Way | Valley Road | Sutro Street | 7/3 |
Silverada Boulevard | Ninth Street | Oddie Boulevard | 7/3 |
Pavement Striping 7:00 p.m. – 7:00 a.m.
STREET | FROM | TO | DATE |
Asti Lane | Bennie Lane | Ferrari McLeod Boulevard | 6/30 |
Parr Circle | Parr Boulevard (W) | Parr Boulevard (E) | 6/30 |
Ormand Court | Giroux Street | Cul-de-sac | 6/30 |
Evans Avenue | Second Street | Jodi Drive | 7/1 |
Stoker Avenue | Fourth Street | Seventh Street | 7/2 |
Summit Ridge Interchange | Summit Ridge | McCarran ROW Fence | 7/2 |
Timber Way | Valley Road | Sutro Street | 7/3 |
Silverada Boulevard | Ninth Street | Oddie Boulevard | 7/3 |
Pavement Markings (Thermoplastic)
STREET | FROM | TO | DATE |
E Victorian Avenue | Stanford Way | McCarran Boulevard | 7/1-3 |
Victorian Avenue | Pyramid Way | Stanford Way | 7/1-3 |
Deming Way | Greg Street | Glendale Avenue | 7/1-3 |
Liberty Street | Center Street | Holcomb Avenue | 7/1-3 |
Asti Lane | Bennie Lane | Ferrari McLeod Boulevard | 7/3 |
Parr Circle | Parr Boulevard (W) | Parr Boulevard (E) | 7/3 |
Ormand Court | Giroux Street | Cul-de-sac | 7/3 |
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Las Brisas Boulevard between Brittania Drive and McCarran Boulevard
- Work will resume June 2024. Slurry seal is anticipated to occur during the week of 06/24, with stripping to follow the week of 07/01.
- One-way traffic control will be implemented.
- Traffic will flow in the westbound direction with a detour at Montego Drive.
- Business access will be maintained.
Los Altos Parkway between North Vista Boulevard and Goodwin Road
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout July.
- Two-way traffic control anticipated to be maintained.
1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Project is substantially complete but there will be some temporary traffic controls in place for final cleanup and punch list items.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Intermittent lane shifts for punch item list work and landscape work.
Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):
- Intermittent lane shifts for punch item list work and landscape work.
Phase 3 – east of US 395 Ramps to Sutro Street (Reno):
- No construction work during Reno Rodeo 2024
Phase 4 – Sutro Street to I-80 Ramps (Reno):
- No construction work during Reno Rodeo 2024.
- Construction activities expected to resume in July.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- Night work is anticipated with closure and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.
- Traffic shift (northbound lane closed) through July 31.
- Removal of sidewalk and driveways.
SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Project is substantially complete.
- All traffic lanes are open in both directions.
STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844
This project is substantially complete.
TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work is substantially complete at the Moana Lane/ Baker Lane, and Prater Way/ 4th Street intersections. Motorists may see occasional shoulder and lane closures for final work items.
SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work is substantially completed on Baring Boulevard, Los Altos Parkway, and Vista Boulevard. Additional work to install fiber optic along Galleria Parkway is expected to begin in July.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. Initial paving operations will begin on June 27 through July 3, from 7:00 a.m. – 7:00 p.m. Work will not take place on Saturday or Sunday.
Through traffic is encouraged to use an alternate route, if possible, while the following traffic control restrictions are in place.
July 1 – July 5
- Eastbound Steamboat Parkway will be reduced to one lane between Damonte Ranch and Veterans Parkway.
- Northbound Veterans Parkway will be reduced to one lane from south of Wind Ranch Road through the intersection of Veterans Parkway and Steamboat Parkway.
- Westbound Steamboat Parkway and Southbound Veterans Parkway will not be impacted.
SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closure on eastbound South Meadows Parkway between Double R Boulevard and Veterans Parkway near I-580.
- Nightly lane closures, June 26, 27, and 28 from 9:00 p.m. to 5:00 a.m. on eastbound Damonte Ranch Parkway between Old Virginia Road and Double R Boulevard.
NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 335–1865
Construction is expected to begin May 28.
June 11 to July 5
- One travel lane in each direction will be maintained on Virginia Street.
- Shoulder closures for southbound and northbound traffic through project limits.
- No on-street parking.