2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Pavement Patching
STREET | TO | FROM | DATE |
Bennie Lane | Gardella Avenue | Parr Boulevard | 6/10 |
Ferrari McLeod Boulevard | Gardella Avenue | Parr Boulevard | 6/10-11 |
Timber Way | Valley Road | S Sutro Street | 6/11 |
Washington Street | Fifth Street | Rancho San Raphael Park | 6/11 |
Calle De La Plata | Encanto Drive | Pyramid Highway | 6/11 |
Keystone Avenue | Seventh Street | Coleman Drive | 6/12-14 |
Mount Charleston Street | Stead Boulevard | Echo Avenue | 6/12-13 |
Stead Boulevard | Silver Lake Road | Silver Lake Road | 6/12-13 |
El Rancho Drive | Prater Way | N of Roundabout | 6/13-14 |
Ormand Court | Giroux Street | End of cul-de-sac | 6/13-14 |
Sullivan Lane | Prater Way | El Rancho Boulevard | 6/14 |
Rock Boulevard | Victorian Avenue | McCarran Boulevard | 6/14 |
Bravo Avenue | McClellan Street | Albert Way | 6/14 |
Micro-Surfacing
STREET | FROM | TO | DATE |
Kuenzki Street | Kietzke Lane | Giroux Street | 6/10 |
Sierra Highlands Drive | S McCarran Boulevard | Idlebury Way | 6/10 |
Mount Rose Street | Arlington Avenue | S Virginia Street | 6/11 |
Ralston Street | Second Street | Fifth Street | 6/11 |
Holcomb Avenue | S Virginia Street | Mill Street | 6/12 |
Neil Road | S McCarran Boulevard | Gentry Way | 6/13 |
Dickerson Road | Second Street | Second Street | 6/14 |
Pavement Striping 7:00 p.m. – 7:00 a.m.
STREET | FROM | TO | DATE |
Kuenzli Street | Kietzke Lane | Giroux Street | 6/10 |
Sierra Highlands Drive | S McCarran Boulevard | Idelbury Way | 6/10 |
Mount Rose Street | Arlington Avenue | Virginia Street | 6/11 |
Ralston Street | Second Street | Fifth Street | 6/11 |
Holcomb Avenue | S Virginia Street | Mill Street | 6/12 |
Neil Road | S McCarran Boulevard | Gentry Way | 6/13 |
Dickerson Road | Second Street | Second Street | 6/14 |
Pavement Markings (Thermoplastic)
STREET | FROM | TO | DATE |
Peckham Lane | Lakeside Drive | Baker Lane | 6/10 |
Crummer Lane | Gate I-580 Right of Way | S Virginia Street | 6/10 |
Regency Way | S Virginia Street | Island of Roundabout | 6/11 |
Lakeside Drive | Evans Creek Road | Moana Lane | 6/11-12 |
Gentry Way | Brinkby Avenue | Chris Lane | 6/11-12 |
Kuenzli Street | Kietzke Lane | Giroux Street | 6/13 |
Sierra Highlands Drive | S McCarran Boulevard | Idlebury Way | 6/13 |
Mount Rose Street | Arlington Avenue | S Virginia Street | 6/14 |
1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Project is substantially complete but there will be some temporary traffic controls in place for final cleanup and punch list items.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Phase 1 – Pyramid Way to Sullivan Lane (Sparks):
- Intermittent lane shifts for punch item list work and landscape work.
Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):
- Intermittent lane shifts for punch item list work and landscape work.
Phase 3 – east of US 395 Ramps to Sutro Street (Reno):
- Lane shifts/closures for punch item list work, landscape work, and NVE lights installations.
Phase 4 – Sutro Street to I-80 Ramps (Reno):
- One lane each direction.
- Lane closures for raising utilities, final concrete and driveway work, landscaping, punch item list work, and NVE lights installations.
- No construction work during Reno Rodeo 2024.
For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com
SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Project is substantially complete.
- All traffic lanes are open in both directions.
STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844
This project is substantially complete.
TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Moana Lane and Baker Lane/Smith Drive (Reno)
The following traffic control will be in place at the intersection of Moana Lane, Baker Lane, and Smith Drive for traffic signal installation:
- Intermittent lane and shoulder closures.
- Full closure of the Smith Drive approach will occur at times. A detour will be provided.
- Full closure of the Baker Lane approach will also occur due to an adjacent project. Follow the signed detour.
Prater Way and 4th Street (Sparks)
The following traffic control will be in place at the intersection of Prater Way and 4th Street for traffic signal replacement:
- Various lane and shoulder closures.
- All turning movements and driveways will remain open.
SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Construction is underway and will continue through June. Motorists can expect the following traffic controls:
Baring Boulevard between Sparks Boulevard and Vista Boulevard
- Various lane and shoulder closures for fiber optic installation.
- Lane closures (if needed) will occur Monday thru Friday, 9:00 a.m. – 3:00 p.m. daily.
Los Altos Parkway between Ion Drive and Sparks Boulevard
- Various shoulder closures for fiber optic installation
- Intermittent closure of the Table Mountain Way approach to Sparks Boulevard. A signed detour will be provided for any closures.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. Traffic is shifted to the center of Steamboat Parkway between Veterans Parkway and Marketplace Drive.
June 10 to June 14
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closure on westbound Damonte Ranch Parkway between Promenade Way and Double R Boulevard, 7:00 a.m. to 7:00 p.m.
- Single lane closure on eastbound South Meadows Parkway between Double R Boulevard and Veterans Parkway near I-580
NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 335–1865
Construction is expected to begin May 28.
May 28 to June 28
- One travel lane in each direction will be maintained on Virginia Street.
- Shoulder closures for southbound and northbound traffic through project limits.
- No on-street parking.