2025 PREVENTATIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-187
Crack Seal
| STREET | FROM | TO | DATE |
| Redfield Parkway | Kietzke Lane | S Virginia Street | 11/17-21 |
| Caughlin Parkway | S McCarran Boulevard | Sierra Crest Way | 11/17-21 |
| Susileen Drive | Marthiam Avenue | Meridian Lane | 11/17-21 |
| Grove Street | Wrondel Way | Kietzke Lane | 11/17-21 |
| Lymbery Street | Cadillac Place | Lakeside Drive | 11/17-21 |
| Vassar Street | S Virginia Street | Kieztke Lane | 11/17-21 |
ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
- Arlington Avenue will close between West 1st Street and Island Avenue.
- Northbound traffic will be detoured to Virginia Street or Center Street.
- Southbound traffic and pedestrians will be detoured to the Sierra Street Bridge.
- West Street will be open to westbound traffic only between West Street and Stevenson Street.
- Wingfield Park will remain closed from May 5, 2025, until summer 2026.
- River recreation detours will also be in place.
- View detour maps at ArlingtonBridges.com
ARROWCREEK PARKWAY & WEDGE PARKWAY REHABILITATION
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
November 15 – November 22
Work on Wedge Parkway will continue through the week of November 17. Paving operations may extend into the week of 11/17. Work will continue on the Shared Use Path.
Arrowcreek Parkway
Work on Arrowcreek Parkway is substantially complete.
Wedge Parkway – Phase 3C Northbound Reconstruction (Mt Rose Highway to White Creek Lane)
- Wedge Parkway will have one-way traffic maintained in the southbound direction.
- The northbound lane closure began on 11/05 and is anticipated to last approximately (2) weeks.
- Access will be maintained to neighborhood streets; however, during the pulverizing and paving operations side street access directly off Wedge Parkway may be inaccessible for a duration of up to (1) hour.
- At least one entrance will remain accessible for neighborhoods and businesses with multiple access points.
- Construction will occur in phases for neighborhoods and businesses with single access points.
- Flagger controls will be in place. Follow business access signs for access to the Galena Junction (Raley’s) Shopping Center.
- Vehicles and pedestrians should follow posted detours; please use alternate routes such as Arrowcreek Parkway, Thomas Creek Road, and S. Virginia Street.
- Normal working hours are from 7:00 a.m. – 6:00 p.m., Monday through Friday
- Work may be extended outside of normal working hours during placement of HMA.
- Work is scheduled to occur on Saturday, 11/15, weather permitting.
- Two-way traffic control with intermittent closures will be maintained
- Work is scheduled to occur on Saturday, 11/22, weather permitting
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-184
Lane Closures
Drivers may see single lane closures on Mill Street or Kietzke Lane. Side street access at Mill Street from either Redwood Place or Louise Street may be closed for utility installation. Please use signed detours.
Bus Stop Closures
RTC RIDE bus service may be temporarily impacted within the project area. Detours or changes to bus stop locations will be noted in advance at the affected bus stop and at https://rtcwashoe.com/alerts/
In the event of a closure, riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.
Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.
PYRAMID HIGHWAY OPERATIONS IMPROVEMENTS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
November 17 – November 25
To advance design of the Pyramid Highway Operations Improvements Project, a contractor will be on site to complete potholing activities in the NDOT right-of-way along Pyramid Highway from Ingenuity Avenue to Egyptian Drive.
- A minimum of one paved travel lane will be open in each direction. With the exception of a possible one-way configuration with flagger assistance when work is performed at the Calle de la Plata/Pyramid Highway intersection.
- Short traffic delays may occur
- Access will be maintained to adjacent properties
- Normal working hours are from 7:00 a.m. – 3:30 p.m., Monday – Friday provided all through lanes of traffic are unrestricted by potholing activity.
- normal working hours are from 9:00 p.m. – 5:30 a.m., Sunday night – Friday morning where traffic is restricted by potholing activities.
- No work is planned over the Thanksgiving Day holiday
- Vehicles, pedestrians, and cyclists should follow posted detours and utilize alternate routes where available.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction will continue through June 2027. Project limits are from intersection of Sparks Boulevard/I80 westbound ramps to the intersection of Sparks Boulevard/ Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com), or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
November 17 – November 21
The community can expect the following traffic control:
Southbound (9:00 a.m. – 7:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Baring Boulevard
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Prater Way.
Northbound (5:00 a.m. – 2:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between Springland Drive and Prater Way
- Single lane closure Sparks Boulevard between Springland Drive and Baring Boulevard
Howard Drive Detour
- Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive.
TRAFFIC SIGNAL FIBER 25-01
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Installation of traffic fiber on Vista Boulevard from Prater Way to Baring Boulevard, Longley Lane from Maestro Drive to S. McCarran Boulevard, Kietzke Lane from Fisherman’s Park to Galletti Way, and Galletti Way from Kietzke Lane to Glendale Avenue.
Vista Boulevard
- Single lane closures for trenching operations.
Longley Lane
- Intermittent lane restrictions for miscellaneous construction.
Kietzke Lane & Galletti Way
- Intermittent lane restrictions for miscellaneous construction.
TRAFFIC SIGNAL MODIFICATIONS 25-01
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
Working hours for the project are 7:00 a.m. – 7:00 p.m., Monday – Friday. This project contains multiple locations of work.
Baring Boulevard/Truckee Lane
Work begins at this intersection for the installation of new traffic signal poles and other equipment on Baring Boulevard. During working hours, the outside westbound lane on Baring Boulevard will be closed intermittently from Rockwood Drive to McCarran Boulevard. One lane of traffic will remain open at all times.
E. Greg Street/Kleppe Lane
Work begins at this intersection for the installation of new traffic signal poles and other equipment on E. Greg Street and Kleppe Lane. During working hours, the outside lanes on E. Greg Street will be closed intermittently in both directions from approximately 500 feet east of Kleppe Lane to the I-80/Vista Drive Interchange. One lane of traffic will remain open at all times in both directions.
Robb Drive/Seventh Street
Pole foundations complete for 3 locations on Robb Drive and Seventh Street. Work will be paused at these locations until December as crews wait on scheduling to complete concrete work. Crews will begin work at other locations during this time.
Mayberry Drive/Hunter Lake Drive
Pole foundations are complete for the installation of school zone flashers on Mayberry Drive and an emergency vehicle flasher at Fire Station No. 5. Work will be paused at these locations while we wait for arrival of flasher poles and equipment. Crews will begin work at other locations during this time.
Upcoming Work:
Work will begin at the intersections of El Rancho Drive/Wedekind Road on December 1.
VETERANS ROUNDABOUT MODIFICATIONS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
November 17 – November 21
Construction is Substantial Completion. During the week of 11/17, work items will include: remaining light pole installation and punch list work.
VISTA AND DISC INTERSECTION IMPROVEMENT PROJECT
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work on the new turn lanes is substantially complete and the lanes are open to traffic. Please use caution around the intersection as minor work items occur.
Final traffic signal upgrades and road striping work will occur in the first half of 2026 when temperatures are warmer.
WEST FOURTH STREET DOWNTOWN
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Crews will be working on the north side of Fourth Street between West Street and Keystone Avenue. Westbound outside lane will be closed in certain areas to provide a work zone buffer. Traffic impacts should be minimal but slow down for workers.