November 22

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Crack Sealing 7:00PM – 7:00AM

STREETFROMTODATE
Lake StreetMill StreetSixth Street11/18-22
Sinclair StreetHolcomb AvenueMill Street11/18-22
Second StreetVirginia Street Giroux Street11/18-22
Lakeside DriveMoana LaneBrinkby Avenue11/18-22
Washington StreetSecond StreetRiverside Drive11/18-22
Mill StreetLake StreetTerminal Way11/18-22
Orovada StreetCity LimitsGreenbrae Drive11/18-22
Wedekind RoadRound-a-boutRound-a-bout11/18-22
Wedekind RoadLund LaneCity Limits11/18-22
Wedekind RoadSullivan LaneEl Rancho Drive11/18-22
15th StreetVictorian AvenueC Street11/18-22
El Rancho DriveWedekind RoadS McCarran Boulevard11/18-22
Kietzke LaneS Virginia StreetCul-de-sac11/18-22
Sierra Rose DriveTalbot RoadKietzke Lane11/18-22
Greg StreetGreg Street BridgeStanford Way11/18-22
Bergin WayKregse LaneEnd11/18-22
Dunn Circle Glendale AvenueWatson Way 11/18-22
Kregse Lane McCarran BoulevardWatson Way11/18-22
Overmeyer RoadBergin WayWatson Way 11/18-22
Watson WayGlendale AvenueDunn Circle11/18-22
Brierley Way Lillard WayVista Boulevard11/18-22
Nugget AvenueMcCarran BoulevardEnd11/18-22
Nugget Court Nugget AvenueEnd11/18-22
Lincoln Way Round-a-boutRound-a-bout11/18-22
Larkin CircleGreg Street BridgePeterbuilt E Driveway11/18-22
Madison AvenueLarkin CircleLarkin Circle11/18-22

SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

November 18 – November 22

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Stripping activities will continue.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape maintenance work.
  • Between US 395 and Sutro Street in Reno:
    • Lane closures for privacy wall work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

November 18 – November 22

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Week of November 18:
    • Crews are expected to work during the day.
    • Raising utilities, miscellaneous asphalt and sidewalk concrete work and landscaping.
  • Traffic Signal at I-580 northbound Exit 29 off-ramp expected to be active the last week in November.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction will continue through Fall 2024. This week crews will be raising utilities and landscaping. Roadway removal and reconstruction is officially complete.

November 18 – November 22

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Damonte Ranch Parkway and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is substantially complete.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

November 17 – November 23

Clear Acre & N. McCarran Boulevard (Reno) – Crews will be performing work on the traffic signal during nighttime hours Sunday evening through Monday morning. Motorists should remain alert and expect lane and shoulder closures near the intersection. At least one lane in each direction will remain open during the nighttime work.

El Rancho & G Street (Sparks) – Motorists should expect changing traffic control conditions Monday through Friday as crews complete roadway pavement markings around the intersection. Isolated shoulder closures and lane closures will be implemented at the intersection during day time working hours, though all movements will remain open and at least one lane of travel will be maintained in each direction on both El Rancho and G Street.

Plumb & Plumas (Reno): The southeast shoulder will be closed and isolated lane reductions on Plumb Lane and Plumas Streets may be implemented Monday through Wednesday during daytime working hours. Pedestrians should follow the signed detour route around the closure.

Robb & Mae Anne (Reno): The southwest shoulder will be closed and isolated lane reductions on Robb Drive and Mae Anne Avenue may be implemented during daytime working hours. Pedestrians should follow the signed detour route around the closure.

Golden Valley & North Hills (Reno): The northwest shoulder will be closed and isolated lane reductions on Golden Valley Road and North Hills Boulevard may be implemented during daytime working hours. Pedestrians should follow the signed detour route around the closure.