2025 PREVENTATIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-187
Utility Raising
| STREET | FROM | TO | DATE |
| University Way | Truckee River Bridge | Maple Street | 11/08 |
Crack Seal (Night Work 7pm – 7am)
| STREET | FROM | TO | DATE |
| Veterans Parkway | South Meadows Parkway | Pembroke | 11/02-06 |
| Pembroke Drive | Rosewood Clubhouse | Boynton Slough Bridge | 11/02-06 |
| West Calle de la Plata | Pyramid Highway | Isidor Street | 11/02-06 |
| La Posada Drive | Omni Drive | Cordoba Boulevard | 11/02-06 |
| Calle de Oro Parkway | Cordoba Boulevard | Cordoba Boulevard | 11/02-06 |
| Kiley Parkway | Pyramid Highway | Windmill Farms Parkway | 11/02-06 |
| Airmotive Way | Villanova Street | Terminal Way | 11/02-06 |
| Harvard Way | Automotive Way | Market Street | 11/02-06 |
| Sunshine Lane | Mill Street | Cul-de-Sac | 11/02-06 |
| Crane Way | 18th Street | Bridge Deck | 11/02-06 |
| Nugget Avenue | Victorian Plaza Circle | Pyramid Way | 11/02-06 |
| Icehouse Avenue | W End | E End | 11/02-06 |
| Freeport Boulevard | 21st Street | Steneri Way | 11/02-06 |
| Sterneri Way | Freeport Boulevard | Glendale Avenue | 11/02-06 |
| Stanford Way | Railroad | Glendale Avenue | 11/02-06 |
| Wolverine Way | Glendale Avenue | Stanford Way | 11/02-06 |
| Southern Way | Greg Street | Freeport Boulevard | 11/02-06 |
| Linda Way | Coney Island Drive | Glendale Avenue | 11/02-06 |
| Coney Island Drive | Marietta Way | Stanford Way | 11/02-06 |
| Spice Island Drive | E Greg Street | Franklin Way | 11/02-06 |
| Moana Lane | Plumas Street | Baker Lane | 11/02-06 |
| Moana Lane | DD Interchange | Neil Road | 11/02-06 |
| Kuenzli Street | Wills Avenue | Second Street | 11/02-06 |
| Liberty Street | Arlington Avenue | Ryland Street | 11/02-06 |
ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
- Arlington Avenue will close between West 1st Street and Island Avenue.
- Northbound traffic will be detoured to Virginia Street or Center Street.
- Southbound traffic and pedestrians will be detoured to the Sierra Street Bridge.
- West Street will be open to westbound traffic only between West Street and Stevenson Street.
- Wingfield Park will remain closed from May 5, 2025, until summer 2026.
- River recreation detours will also be in place.
- View detour maps at ArlingtonBridges.com
ARROWCREEK PARKWAY & WEDGE PARKWAY REHABILITATION
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
November 01 – November 08
Work on Wedge Parkway will continue through the week of November 3. During this time, Granite will continue to construct concrete improvements on the east side of Wedge Parkway, including: curb, gutter, pedestrian ramps and aprons. Utilities will be lowered in the northbound direction and potholing will occur in the northbound direction. Work will continue on the Shared Use Path on the east side of Wedge Parkway. Striping will occur in the newly paved southbound lane on 11/04. On 11/05 paving operation swill start in the northbound lane.
Arrowcreek Parkway
Work on Arrowcreek Parkway is substantially complete.
Wedge Parkway – Phase 3C Northbound Reconstruction (Mt Rose Highway to White Creek Lane)
- Wedge Parkway will have one-way traffic maintained in the southbound direction in the southbound lane.
- Access will be maintained to neighborhood streets; however, during the pulverizing and paving operations side street access directly off Wedge Parkway may be inaccessible for a duration of up to (1) hour.
- At least one entrance will remain accessible for neighborhoods and businesses with multiple access points.
- Construction will occur in phases for neighborhoods and businesses with single access points.
- Flagger controls will be in place. Follow business access signs for access to the Galena Junction (Raley’s) Shopping Center.
- Vehicles and pedestrians should follow posted detours; please use alternate routes such as Arrowcreek Parkway, Thomas Creek Road, and S. Virginia Street.
- Normal working hours are from 7:00 a.m. – 6:00 p.m., Monday through Friday
- Work is scheduled to occur on Saturday, 11/01/25, weather permitting.
- Two-way traffic control with intermittent closures will be maintained
- Work is scheduled to occur on Saturday, 11/08/25, weather permitting
- Concrete improvements will be constructed in the northbound direction and paving operations will continue in the northbound direction.
- Phase 3C traffic control (one-way traffic in the southbound direction), will be maintained to complete this work.
- Work is scheduled to occur on Saturday, 11/01/25, weather permitting.
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-184
Mill Street Lane Shifts
Mill Street is restriped in a new temporary lane configuration from west of Kietzke Lane to I-580 and the speed limit is reduced to 30 mph. Drivers are asked to use caution through lane shifts and note changes to turn lanes at the Mill/Kietzke intersection. No on-street parking is allowed in this area. These temporary traffic conditions will be in place through 2025.
Drivers will see single lane closures in the vicinity of Mill Street/Kietzke Lane.
Bus Stop Closures
RTC RIDE bus service may be temporarily impacted within the project area. Detours or changes to bus stop locations will be noted in advance at the affected bus stop and at https://rtcwashoe.com/alerts/
In the event of a closure, riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.
Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction will continue through June 2027. Project limits are from intersection of Sparks Boulevard/I80 westbound ramps to the intersection of Sparks Boulevard/ Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com), or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
November 3 – November 7
The community can expect the following traffic control:
Southbound (9:00 a.m. – 7:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Baring Boulevard
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Prater Way.
Northbound (5:00 a.m. – 2:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between Springland Drive and Prater Way
- Single lane closure Sparks Boulevard between Springland Drive and Baring Boulevard
Howard Drive Detour
- Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive.
TRAFFIC SIGNAL FIBER 25-01
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Installation of traffic fiber on Vista Boulevard from Prater Way to Baring Boulevard, Longley Lane from Maestro Drive to S. McCarran Boulevard, Kietzke Lane from Fisherman’s Park to Galletti Way, and Galletti Way from Kietzke Lane to Glendale Avenue.
Vista Boulevard
- Intermittent lane restrictions for miscellaneous construction.
Longley Lane
- Intermittent lane restrictions for miscellaneouse construction.
Kietzke Lane & Galletti Way
- Single lane closures for trenching operations.
TRAFFIC SIGNAL MODIFICATIONS 25-01
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
November 03 – November 07
Work begins for the installation of overhead school zone flashers on Robb Drive and on 7th Street near McQueen High School. Working hours for the project at 7:00 a.m. – 7:00 p.m., Monday – Friday.
During these times expect intermittent closures of the outside lane in either direction on Robb Drive (between Mae Anne Avenue and Blue Canyon Drive) and on 7th Street (between Robb Drive and Painted Cliff Drive/Stargaze Way). Once lane of traffic in both directions will remain open at all times.
VETERANS ROUNDABOUT MODIFICATIONS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
November 03 – November 07
During the week of 11/03, work items will generally include: RRFB and light pole installation, striping and punch list work.
- A minimum of one paved travel lane will be open in each direction.
- Left turn lanes at all signalized intersections will be open.
- Short traffic delays may occur during this phase of construction.
- Access will be maintained to adjacent properties.
- Temporary driveway closures may occur during certain construction activities; and if so, Q&D will provide notice to impacted properties 18-24 hours prior to start of work.
- Normal working hours are from 7:00 a.m. to 7:00 p.m., Monday through Friday.
- Work will not occur on 10/31/2025 in observance of the Nevada Day Holiday.
- Vehicles and pedestrians should follow posted detours.
- Alternate routes, such as utilizing S. Virginia St and newly improved Steamboat Pkwy, are encouraged in an ongoing effort to alleviate traffic through the work zone when possible.
VISTA AND DISC INTERSECTION IMPROVEMENT PROJECT
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work on the new turn lanes is substantially complete and the lanes are open to traffic. Please use caution around the intersection as minor work items occur.
Final traffic signal upgrades and road striping work will occur in the first half of 2026 when temperatures are warmer.
VISTA PRATER SIGNAL FIBER CONNECTION PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Project is substantially complete.
WEST FOURTH STREET DOWNTOWN
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Crews will be working on the north side of Fourth Street between West Street and Keystone Avenue. Westbound outside lane will be closed in certain areas to provide a work zone buffer. Traffic impacts should be minimal but slow down for workers.