2025 PREVENTATIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-187
Utility Raising
| STREET | FROM | TO | DATE |
| Cashill Boulevard | S McCarran Boulevard | Skyline Boulevard | 10/28 |
| California Avenue | Hunter Lake Drive | S Virginia Street | 10/28 |
Crack Seal (Night Work 7pm – 7am)
| STREET | FROM | TO | DATE |
| White Lake Parkway | W Mile Marker | Village Parkway | 10/26-30 |
| Red Rock Road | US 395 North Row | Moya Boulevard | 10/26-30 |
| Panther Drive | S Virginia Street | Western Road | 10/26-30 |
| Parr Boulevard | S Virginia Street | US 395 | 10/26-30 |
| Seventh Avenue | W Sun Valley Drive | Golden Valley Drive | 10/26-30 |
| Arrowcreek Parkway | Thomas Creek Road | Private Entrance | 10/26-30 |
| Damonte Ranch Parkway | Double R Boulevard | Steamboat Parkway | 10/26-30 |
| Veterans Parkway | South Meadows Parkway | Pembroke Drive | 10/26-30 |
| Pembroke Drive | Rosewood Clubhouse | Boynton Slough Bridge | 10/26-30 |
| Golden Valley Road | Spearhead Drive | Opal Station Drive | 10/26-30 |
| Isidor Court | Calle de la Plata | Circuit Court | 10/26-30 |
| Calle de la Plata | Pyramid Highway | Isidor Street | 10/26-30 |
| La Posada Drive | RAB Omni Drive | Cordoba Boulevard | 10/26-30 |
| Calle de Oro Parkway | Cordoba Boulevard | Cordoba Boulevard | 10/26-30 |
| Kiley Parkway | Pyramid Highway | Windmill Farms Parkway | 10/26-30 |
| Airmotive Way | Villanova Street | Terminal Way | 10/26-30 |
| Harvard Way | Automotive Way | Market Street | 10/26-30 |
| Sunshine Lane | Mill Street | Cul-d-Sac | 10/26-30 |
| Crane Way | 18th Street | Bridge Deck | 10/26-30 |
| Nugget Avenue | Victorian Plaza Circle | Pyramid Way | 10/26-30 |
ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
- Arlington Avenue will close between West 1st Street and Island Avenue.
- Northbound traffic will be detoured to Virginia Street or Center Street.
- Southbound traffic and pedestrians will be detoured to the Sierra Street Bridge.
- West Street will be open to westbound traffic only between West Street and Stevenson Street.
- Wingfield Park will remain closed from May 5, 2025, until summer 2026.
- River recreation detours will also be in place.
- View detour maps at ArlingtonBridges.com
ARROWCREEK PARKWAY & WEDGE PARKWAY REHABILITATION
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
October 25 – October 31
Work on Wedge Parkway will continue through this week. During this time, Granite will continue to construct concrete improvements on the east side of Wedge Parkway including: curb, gutter and sidewalk. Utilities will be lowered in the northbound direction. Work will continue on the Shared Use Path on the east side of Wedge Parkway. Two-way traffic with intermittent closures will be maintained.
Arrowcreek Parkway
Work on Arrowcreek Parkway is substantially complete.
Wedge Parkway
- Two-way traffic with intermittent closures will be maintained throughout the week
- Vehicles and pedestrians should follow posted detours; please use alternate routes such as Arrowcreek Parkway, Thomas Creek Road, and S. Virginia Street.
- Normal working hours are from 7:00 a.m. – 6:00 p.m., Monday through Friday
- No work will occur Friday, 10/31/2025 in observance of the Nevada Day Holiday.
- Work is scheduled to occur on Saturday, 10/25/2025 to complete striping in the southbound lane, weather permitting.
- One-way traffic will be maintained in the northbound direction in the northbound lane
- The southbound lane of Wedge Parkway will be closed from Mt. Rose Highway to approximately the south side of the reno Ice/Meadows Shopping Center.
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-184
Mill Street Lane Shifts
Mill Street is restriped in a new temporary lane configuration from west of Kietzke Lane to I-580 and the speed limit is reduced to 30 mph. Drivers are asked to use caution through lane shifts and note changes to turn lanes at the Mill/Kietzke intersection. No on-street parking is allowed in this area. These temporary traffic conditions will be in place through 2025.
Drivers will see single lane closures in the vicinity of Mill Street/Kietzke Lane.
Bus Stop Closures
RTC RIDE bus service may be temporarily impacted within the project area. Detours or changes to bus stop locations will be noted in advance at the affected bus stop and at https://rtcwashoe.com/alerts/
In the event of a closure, riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.
Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction started Monday, September 15, 2025, and will continue through June 2027. Project limits are from intersection of Sparks Boulevard/I80 westbound ramps to the intersection of Sparks Boulevard/ Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com), or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
October 27 – October 31
The community can expect the following traffic control:
Southbound (9:00 a.m. – 7:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Baring Boulevard
- Single lane closure Sparks Boulevard between O’Callaghan Drive and Prater Way.
Northbound (5:00 a.m. – 2:00 p.m. Monday – Friday)
- Single lane closure Sparks Boulevard between Springland Drive and Prater Way
- Single lane closure Sparks Boulevard between Springland Drive and Baring Boulevard
Howard Drive Detour
- Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive.
TRAFFIC SIGNAL FIBER 25-01
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Installation of traffic fiber on Vista Boulevard from Prater Way to Baring Boulevard, Longley Lane from Maestro Drive to S. McCarran Boulevard, Kietzke Lane from Fisherman’s Park to Galletti Way, and Galletti Way from Kietzke Lane to Glendale Avenue.
Vista Boulevard
- Intermittent lane restrictions for miscellaneous construction.
Longley Lane
- Intermittent lane restrictions for miscellaneouse construction.
Kietzke Lane & Galletti Way
- Single lane closures for trenching operations.
VETERANS ROUNDABOUT MODIFICATIONS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
October 27 – October 31
Work items generally include: construction of concrete improvements, RRFB and light pole installation, placement of decorative rock and structures, and installation of signs.
- A minimum of one paved travel lane will be open in each direction.
- Left turn lanes at all signalized intersections will be open.
- Short traffic delays may occur during this phase of construction.
- Access will be maintained to adjacent properties.
- Temporary driveway closures may occur during certain construction activities; and if so, Q&D will provide notice to impacted properties 18-24 hours prior to start of work.
- Normal working hours are from 7:00 a.m. to 7:00 p.m., Monday through Friday.
- Work will not occur on 10/31/2025 in observance of the Nevada Day Holiday.
- Vehicles and pedestrians should follow posted detours.
- Alternate routes, such as utilizing S. Virginia St and newly improved Steamboat Pkwy, are encouraged in an ongoing effort to alleviate traffic through the work zone when possible.
VISTA AND DISC INTERSECTION IMPROVEMENT PROJECT
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Motorists can expect the following traffic impacts Mondays thru Fridays, for construction of new and extended turn lanes at the Vista Blvd and Disc Dr intersection:
- Various lane closures on Disc Drive between Sparks Boulevard and Vista Boulevard.
- Various lane closures on Vista Boulevard between Iratcabal Drive and Caledonian Drive
- Southbound Vista closures will occur between 9:00 a.m. – 5:00 p.m.
- Northbound Vista closures will occur between 7:00 a.m. – 3:00 p.m.
- Periodic closure of driveways to access the Spanish Springs Center will be necessary. Access to this shopping center will be available via alternate driveways along Disc Drive and Vista Boulevard with signage provided.
- Various sidewalk closures will also be in effect along Vista Boulevard and Disc Drive. Pedestrian detours will be signed as needed.
Work is expected to continue through the end of October.
VISTA PRATER SIGNAL FIBER CONNECTION PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Project is substantially complete.