2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Pavement Patching
STREET | FROM | TO | DATE |
South Virginia Street | McCarran Boulevard | Longley Lane | 9/23-25 |
Thermoplastic Installation
STREET | FROM | TO | DATE |
Montello Street | End of Fence | Sixth Street | 9/23 |
Ninth Street | Evans Street | Valley Road | 9/23 |
Vassar Street | Kietzke Lane | Harvard Way | 9/23 |
Sugar Pine Court | Cul-de-Sac | Woodland Avenue | 9/24 |
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
September 23 – September 27
- SNC has completed Phase 1 of construction – lowering utilities in preparation of the mill and fill operation to follow.
- There will be no activity this week.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Crews are expected to continue working during the night until October 10, paving the northbound land and removing/replacing concrete (curb/gutter/ped/ramps/driveways) and installing conduit, pull boxes, poles, etc. )electrical work) at the intersection of Patriot Boulevard/South Virginia Street.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. Intersection paving operations are scheduled for Tuesday, September 17 and Wednesday, September 18 at night between 7:00 a.m. to 7:00 p.m. During paving operations, the following traffic control restrictions will be in place. Through traffic is encouraged to use alternate routes, if possible.
September 23 – September 27
- Steamboat Parkway will be reduced to a single lane in the eastbound direction between the intersection of Veterans Parkway/Steamboat Parkway and Dark Horse Road/Steamboat Parkway.
- Steamboat Parkway will be reduced to a single lane in each direction between the intersection of Steamboat Parkways/Marketplace Lane and Steamboat Parkway/Damonte Ranch Parkway.
- Damonte Ranch Parkway will be reduced to a single lane in each direction between the intersection of Steamboat Parkway/Damonte Ranch Parkway and Promenade Way/Damonte Ranch Parkway.
- Southbound Veterans Parkway will be reduced to a single lane at intersection of Veterans Parkway/Steamboat Parkway to appoximately 1,000 feet south of this intersection.
- Northbound Veterans Parkway will be reduced to a single lane from the intersection of Veterans Parkway/Steamboat Parkway to approximately 1,000 feet north of this intersection.
- Anticipate delays and use caution and slow speeds through the work zone.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
September 23 – September 27
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane/2nd Street. This work will occur between the hours of 9:00 p.m. and 5:30 p.m.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
El Rancho Boulevard & G Street
- Intermittent lane closures will occur in all directions at this location as crews work on overhead signal systems and reconstruct the right turn lane from eastbound G Street to southbound El Rancho Boulevard.
- Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.
Clear Acre Lane & McCarran Boulevard
- Shoulder and lane closures during nighttime working hours should be expected as crew’s complete pedestrian improvements on the northeast corner of the intersection.