September 6, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Micro-Surfacing 7:00 a.m. – 5:00 p.m.

STREETFROMTODATE
Los Altos ParkwayVista BoulevardSanta Barbara Avenue09/11
Vista BoulevardLoop RoadBrierley Way9/11

LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

Las Brisas Boulevard between Brittania Drive and McCarran Boulevard

  • Work is substantially complete.
  • Contractor will be on site to complete minor work items throughout August.
  • Two-way traffic anticipated to be maintained.

Los Altos Parkway between North Vista Boulevard and Goodwin Road

  • Work is substantially complete.
  • Contractor will be on site to complete minor work items throughout August.
  • Two-way traffic anticipated to be maintained.


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

September 9 – September 13

  • SNC has completed Phase 1 of construction – lowering utilities in preparation of the mill and fill operation to follow.
  • There will be no activity this week.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Crews will be working during the night until September 20, installing concrete (curb, gutter, pedestrian ramps, and driveways) on the southbound side of South Virginia and installing electrical work ( conduit, pull boxes, poles, etc.).
  • Crews will also start work on the Patriot/S Virginia intersection.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. Intersection paving operations are scheduled for September 9-10 at night between 7:00 p.m. to 5:00 a.m. Druing paving operations, the following traffic control restrictions will be in place. Through traffic is encouraged to use alternate routes, if possible.

September 9 – September 13

  • Veterans Parkway will be closed at Carat Avenue and Rio Wrangler between 7:00 p.m. and 5:00 a.m., Monday night and Tuesday night.
  • Traffic will be reduced to one lane in each direction and under flagger control at the intersection of Steamboat Parkway/Veterans Parkway.
  • Northbound Veterans Parkway will be detoured via Rio Wrangler.
  • Southbound Veterans Parkway will be detoured at Carat Avenue.
  • Anticipate delays and use caution and slow speeds through the work zone.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

September 9 – September 13

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

September 2 – September 6

El Rancho Boulevard & G Street

  • Intermittent lane closures will occur in all directions at this location as crews work o overhead signal systems and reconstruct the right turn lane from eastboud.
  • Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.

Battle Born Way and Galletti Way

  • Crews will begin work on the traffic signal system on Monday, August 20.
  • Reduced lanes in eastbound direction.
  • Shoulder and pedestrian access will be closed on the southeast corner of the intersection during daytime non-peak hours.
  • Intermittent lane closures will occur in all directions as crew work on overhead signal systems.
  • Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.

Los Altos Parkway and Galleria Parkway

  • Intermittent lane closures will occur in all directions as crew work on overhead signal systems.
  • Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.