PROJECT DETAILS
RTC Project No. 247009
RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
(775) 335-1880
awolfson@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: Titan Electrical Contracting
PROJECT DESCRIPTION
Project will expand traffic communication network with fiber optics and will include other ITS infrastructure. An update to the 2016 ITS Master Plan, investigation of Dynamic Message Signs (DMS) coordination and investigation of flow detection/traveler information infrastructure is included in the project.
LATEST NEWS
Construction is substantially complete. Final punch list items are being worked on including testing of new fiber infrastructure.
SCHEDULE
Planning: Complete
Environmental: N/A
Preliminary Design: Complete
Final Design: Winter 2021
Construction: Spring 2023
FINANCIAL INFORMATION
Total Project Estimate:$2,107,000
Funding Source: RTC Fuel Tax
Post updated on: September 29, 2023
ITS Traffic Management Phase 4 Project Map