-
2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET FROM TO DATE Huffaker Lane Del Monte Lane S Virginia Street 10/08 Lakeside Drive Evans Creek Road Moana Lane 10/08 Mount Rose Street Arlington Avenue S Virginia Street 10/09 Holcomb Avenue S Virginia Street Mill Street 10/09 Ralston Street Second Street Fifth Street 10/09 Evans Avenue Second Street Jodi Drive 10/09 Summit Ridge Drive Summit Ridge Court McCarran Boulevard 10/10 Avenida de Landa Sharlands Avenue Robb Drive 10/10 Timber Way Valley Road Sutro Street 10/10 Asti Lane Bennie Lane Ferrari McLeod Boulevard 10/11 Stead Boulevard Silver Lake Road Echo Avenue 10/11 Bravo Avenue Mount McClellan Street Albert Way 10/11 Punch List
STREET FROM TO DATE Vista Boulevard Brierley Way Wingfield Hills Drive 10/10 Sullivan Lane Prater Way El Rancho Boulevard 10/10 Parr Circle Parr Boulevard Parr Boulevard 10/10 Tampa Street Timber Way Timber Way 10/10 Dickerson Road Second Street Second Street 10/10 Holcomb Avenue Virginia Street Mill Street 10/10 Gentry Way Terminal Way Chris Lane 10/10
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
October 7 – October 11
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
- Northbound lane paving – Week of October 7 during the night.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.
October 7 – October 11
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
October 7 – October 11
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897No work will take place this week.
Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.
-
2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET FROM TO DATE Summit Ridge Drive Summit Ridge Court W 4th Street 10/14 Summit Ridge Interchange Summit Ridge Right of Way Fence 10/14 Avenida de Landa Sharlands Avenue Robb Drive 10/14 Timber Way Valley Road Sutro Street 10/14 Asti Lane Bennie Lane Ferrari McLeod Boulevard 10/15 Stead Boulevard Silver Lake Road Echo Avenue 10/15 Bravo Avenue Mount McClellan Street Albert Way 10/15 Ralston Street Second Street Fifth Street 10/16 Wingfield Parkway Vista Boulevard Wingfield Springs Road 10/16-18 Vista Boulevard Brierley Way Wingfield Hills 10/16-18 Pavement Markings
STREET FROM TO DATE Woodland Avenue Sugar Pine Court S 4th Street 10/17
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
October 14 – October 18
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Week of October 14:
- Crews are expected to continue working during the nighttime, installing concrete median, paving median island and removing concrete on Longley Lane and Huffaker Lane.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.
October 14 – October 18
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
- Southbound Veterans Parkway will be reduced to a continuous single lane closure between RC Willey and approximately 150 feet north of the intersection of Steamboat Parkway/Veterans Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
October 14 – October 18
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897No work will take place this week.
Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.
-
2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET FROM TO DATE South Meadows Parkway Double Diamond Parkway Veterans Parkway 10/21 Double R Boulevard Amston Road Longley Lane 10/21 Rock Boulevard Oddie Boulevard McCarran Boulevard 10/22 Sullivan Lane Prater Way Wedekind Road 10/22-23 Pavement Patching
STREET FROM TO DATE South Meadows Parkway Double Diamond Parkway Veterans Parkway 10/22-24 Double R Boulevard Amston Road Longley Lane 10/22-24
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
October 21 – October 25
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Week of October 21:
- Crews are expected to continue working during the nighttime.
- Milling and paving starts the night of October 21-24.
- I-580 exit 29 ramps closures with detours at South Meadows and Neil Road.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.
October 21 – October 25
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
- Southbound Veterans Parkway will be reduced to a continuous single lane closure between Carat Avenue and the intersection of Steamboat Parkway/Veterans Parkway for the next few weeks.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
October 21 – October 25
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897October 21 – October 24
- Work will continue at El Rancho and G Street.
- Motorists should expect daytime shoulder closures and lane restrictions.
- All movements will be open at the intersection and businesses access will remain open during the construction.
- Marked pedestrian detours will be in place to route pedestrians through the work zone.
-
2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET FROM TO DATE Asti Lane Bennie Lane Ferrari McLeod Boulevard 10/30 Stead Boulevard Silver Lake Road Echo Avenue 10/30 Bravo Avenue Mount McClellan Street Albert Way 10/30 Wingfield Parkway Vista Boulevard Wingfield Springs Road 10/31 Vista Boulevard Brierley Way Wingfield Hills Drive 10/31-11/1 Pavement Marking
STREET FROM TO DATE Woodland Avenue Sugar Pine Court Fourth Street 11/02 Crack Sealing
STREET FROM TO DATE Mae Anne Avenue Sharlands Avenue Robb Drive 10/30-11/1 Sierra Highlands Drive Mountcrest Lane Greystone Drive 10/30-11/1 Idlewild Drive Riviera Street Booth Street 10/30-11/1 Arlington Avenue Skyline Boulevard Truckee River Bridge Deck 10/30-11/1 Plumas Street Ridgeview Drive Plumb Lane 10/30-11/1 Lakeside Drive Moana Lane Brinkby Avenue 10/30-11/1
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
October 28 – November 1
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Stripping activities will continue.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Week of October 28:
- Crews are expected to perform landscape work during the day.
- Miscellaneous asphalt and sidewalk concrete work during nighttime.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.
October 28 – November 1
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
- Southbound Veterans Parkway will be reduced to a continuous single lane closure between Carat Avenue and the intersection of Steamboat Parkway/Veterans Parkway for the next few weeks.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139Construction is substantially complete. Crews will be performing miscellaneous work this week. Traffic control impacts will be minimal.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897October 28 – November 1
- Crews will be performing major milling and paving operations at the intersection of El Rancho Drive & G Street.
- G Street to the west of the intersection will be CLOSED to all traffic within 300 feet of the intersection from 7:00 a.m. Monday, October 28 through 5:00 p.m. Friday, November 1.
- Through two-way traffic will be maintained on El Rancho Drive, lanes will be reduced, and drivers may want to use alternate routes.
- All business and residential access will remain open.
- Detour signs will be in place to direct travelers around closure.