Weekly Traffic Control Report


2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
Huffaker Lane Del Monte LaneS Virginia Street10/08
Lakeside DriveEvans Creek RoadMoana Lane10/08
Mount Rose StreetArlington AvenueS Virginia Street10/09
Holcomb AvenueS Virginia StreetMill Street10/09
Ralston StreetSecond StreetFifth Street10/09
Evans AvenueSecond StreetJodi Drive10/09
Summit Ridge DriveSummit Ridge CourtMcCarran Boulevard10/10
Avenida de LandaSharlands AvenueRobb Drive10/10
Timber WayValley RoadSutro Street10/10
Asti LaneBennie LaneFerrari McLeod Boulevard10/11
Stead BoulevardSilver Lake RoadEcho Avenue10/11
Bravo AvenueMount McClellan StreetAlbert Way10/11

Punch List

STREETFROMTODATE
Vista BoulevardBrierley WayWingfield Hills Drive10/10
Sullivan Lane Prater Way El Rancho Boulevard10/10
Parr Circle Parr Boulevard Parr Boulevard10/10
Tampa StreetTimber Way Timber Way10/10
Dickerson RoadSecond StreetSecond Street10/10
Holcomb AvenueVirginia StreetMill Street10/10
Gentry WayTerminal Way Chris Lane10/10


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 7 – October 11

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
  • Northbound lane paving – Week of October 7 during the night.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.

October 7 – October 11

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

October 7 – October 11

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

No work will take place this week.

Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.


2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
Summit Ridge DriveSummit Ridge CourtW 4th Street10/14
Summit Ridge InterchangeSummit RidgeRight of Way Fence10/14
Avenida de LandaSharlands AvenueRobb Drive10/14
Timber WayValley RoadSutro Street10/14
Asti LaneBennie LaneFerrari McLeod Boulevard10/15
Stead Boulevard Silver Lake RoadEcho Avenue10/15
Bravo Avenue Mount McClellan StreetAlbert Way10/15
Ralston StreetSecond StreetFifth Street10/16
Wingfield ParkwayVista BoulevardWingfield Springs Road10/16-18
Vista Boulevard Brierley WayWingfield Hills10/16-18

Pavement Markings

STREETFROMTODATE
Woodland AvenueSugar Pine CourtS 4th Street 10/17


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 14 – October 18

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Week of October 14:
    • Crews are expected to continue working during the nighttime, installing concrete median, paving median island and removing concrete on Longley Lane and Huffaker Lane.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.

October 14 – October 18

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
  • Southbound Veterans Parkway will be reduced to a continuous single lane closure between RC Willey and approximately 150 feet north of the intersection of Steamboat Parkway/Veterans Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

October 14 – October 18

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

No work will take place this week.

Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.


2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
South Meadows ParkwayDouble Diamond ParkwayVeterans Parkway10/21
Double R BoulevardAmston RoadLongley Lane 10/21
Rock BoulevardOddie BoulevardMcCarran Boulevard10/22
Sullivan Lane Prater WayWedekind Road10/22-23

Pavement Patching

STREETFROMTODATE
South Meadows ParkwayDouble Diamond ParkwayVeterans Parkway10/22-24
Double R BoulevardAmston RoadLongley Lane10/22-24


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 21 – October 25

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Week of October 21:
    • Crews are expected to continue working during the nighttime.
    • Milling and paving starts the night of October 21-24.
    • I-580 exit 29 ramps closures with detours at South Meadows and Neil Road.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.

October 21 – October 25

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
  • Southbound Veterans Parkway will be reduced to a continuous single lane closure between Carat Avenue and the intersection of Steamboat Parkway/Veterans Parkway for the next few weeks.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

October 21 – October 25

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

October 21 – October 24

  • Work will continue at El Rancho and G Street.
  • Motorists should expect daytime shoulder closures and lane restrictions.
  • All movements will be open at the intersection and businesses access will remain open during the construction.
  • Marked pedestrian detours will be in place to route pedestrians through the work zone.


2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
Asti Lane Bennie LaneFerrari McLeod Boulevard10/30
Stead Boulevard Silver Lake RoadEcho Avenue10/30
Bravo AvenueMount McClellan StreetAlbert Way10/30
Wingfield ParkwayVista BoulevardWingfield Springs Road10/31
Vista BoulevardBrierley WayWingfield Hills Drive10/31-11/1

Pavement Marking

STREETFROMTODATE
Woodland AvenueSugar Pine CourtFourth Street11/02

Crack Sealing

STREETFROMTODATE
Mae Anne AvenueSharlands AvenueRobb Drive10/30-11/1
Sierra Highlands DriveMountcrest LaneGreystone Drive10/30-11/1
Idlewild DriveRiviera StreetBooth Street10/30-11/1
Arlington AvenueSkyline BoulevardTruckee River Bridge Deck10/30-11/1
Plumas StreetRidgeview DrivePlumb Lane10/30-11/1
Lakeside DriveMoana LaneBrinkby Avenue10/30-11/1


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 28 – November 1

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Stripping activities will continue.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Week of October 28:
    • Crews are expected to perform landscape work during the day.
    • Miscellaneous asphalt and sidewalk concrete work during nighttime.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.

October 28 – November 1

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
  • Southbound Veterans Parkway will be reduced to a continuous single lane closure between Carat Avenue and the intersection of Steamboat Parkway/Veterans Parkway for the next few weeks.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is substantially complete. Crews will be performing miscellaneous work this week. Traffic control impacts will be minimal.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

October 28 – November 1

  • Crews will be performing major milling and paving operations at the intersection of El Rancho Drive & G Street.
  • G Street to the west of the intersection will be CLOSED to all traffic within 300 feet of the intersection from 7:00 a.m. Monday, October 28 through 5:00 p.m. Friday, November 1.
  • Through two-way traffic will be maintained on El Rancho Drive, lanes will be reduced, and drivers may want to use alternate routes.
  • All business and residential access will remain open.
  • Detour signs will be in place to direct travelers around closure.