Weekly Traffic Control Report



2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

PAVEMENT PATCHING

STREETFROMTODATE
Dickerson RdSecond StreetSecond Street5/13
W Grove StLymberry StreetHarvard Way5/13
Edison WayRock BoulevardMill Street5/13-14
Wall StreetCorporate BoulevardFinancial Boulevard5/13-14
Gentry WayTerminal WayNeil Road5/14-15
Neil RoadMcCarran BoulevardGentry way5/14-15
Huffaker Lane (West)Del Monte LaneVirginia Street5/14-16
Lakeside DriveEvans Creek RoadMoana Lane5/14-16
Thomas Creek RoadHolcomb LaneFoothill Road5/15-17
Grove StreetLymberry StHarvard Way5/16-17
Peckham LaneLakeside DriveBaker Lane5/17
Holcomb AvenueVirginia StreetMill Street5/17
Mt Rose Street Arlington AvenueVirginia Street5/17

CRACK SEAL CREW # 1 (NIGHT WORK 7:00 PM – 7:00 AM)

STREETFROMTODATE
Lakeside Drive Evans Creek Road Moana Lane5/12-16
Peckham Lane Lakeside DriveBaker Lane5/12-16
Grove Street Lymberry StreetWrondel Way5/12-16
Grove StreetKietzke Lane Harvard Way5/12-16
Mount Rose StreetArlington AvenueVirginia Street5/12-16
Holcomb AvenueVirginia StreetBurns Street5/12-16
Holcomb AvenueLiberty StreetMill Street5/12-16
Avenida De LandaSharlands AvenueRobb Street5/12-16
Mae Anne AvenueQuail Run RoadMcCarran Boulevard5/12-16
Summit Ridge DriveSummit Ridge CourtWest Fourth Street5/12-16
Summit Ridge InterchangeSummit RidgeRight-of-Way Fence5/12-16
Stoker AvenueFourth StreetSeventh Street5/12-16
Dickerson RoadW/End Second StreetW/End Second Street5/12-16
Ralston StreetSecond StreetFifth Street5/12-16
Liberty Street Center StreetHolcomb Avenue5/12-16
Evans AvenueSecond StreetFourth Street5/12-16
Evans AvenueFreeway OverpassJodi Drive5/12-16
Ninth StreetEvans AvenueValley Road5/12-16
Tampa StreetTimber WayTimber Way5/12-16
Timber WayValley RoadSutro Street5/12-16
Montello StreetE/End Street at FenceSixth Street5/12-16
Kuenzli StreetKietzke LaneGiroux Street5/12-16
Ormand CourtGiroux StreetEnd cul-de-sac5/12-16
Regency WayVirginia StreetEnd of Island W of Roundabout5/12-16
Crummer LaneE/End at Gate I-580 Right-of-WayVirginia Street5/12-16
Huffaker LaneDel Monte LaneVirginia Street5/12-16
Summit Ridge InterchangeSummit RidgeMcCarran Right-of-Way Fence5/12-16

CRACK SEAL CREW #2 (NIGHT WORK 7:00 PM – 7:00 AM)

STREETFROMTODATE
Ohm PlaceMill StreetMill Street05/12-16
Edison WayRock BoulevardMill Street05/12-16
Wall Street Corporate BoulevardFinancial Boulevard05/12-16
Equity AvenueCorporate BoulevardMcCarran Boulevard05/12-16
Bennie LaneGardella AvenueParr Boulevard05/12-16
Asti LaneBennie LaneFerrari Mcleod Boulevard05/12-16
Ferrari Mcleod BoulevardGardella AvenueParr Boulevard05/12-16
Parr CircleParr Boulevard Parr Boulevard05/12-16
Security Circle Virginia StreetVirginia Street05/12-16
Echo CourtEcho AvenueEnd of cul-de-sac05/12-16
Bravo AvenueMount McClellan StreetMount Bismark Street05/12-16
Bravo AvenueMount LolaCity Limit at Albert Way05/12-16
Mount Charleston StreetStead Boulevard Echo Avenue05/12-16
Stead Boulevard Silver Lake RoadEcho Avenue05/12-16
El Rancho DrivePrater WayN of Rab05/12-16
Sullivan LanePrater WayEl Rancho Boulevard05/12-16
Rock BoulevardVictorian Avenue McCarran Boulevard05/12-16
Victorian AvenueStanford WayMcCarran Boulevard05/12-16
Victorian AvenuePyramid WayStanford Way05/12-16
Vista Boulevard Wingfield HillsWingfield Hills Drive05/12-16

1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Project is substantially complete but there will be some temporary traffic controls in place on occasion as the contractor addresses final cleanup and punch list items.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Construction is complete. Minor punch item list work and landscape maintenance taking place after Phase 4 (expected by mid May).

Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):

  • Major construction completed.
  • Intermittent one lane closures.
  • Landscape, permanent striping, and punch list items.

Phase 3 – east of US 395 Ramps to Sutro Street (Reno):

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Lane closures. One lane in each direction.
  • Roadwork and paving between Sutro Street and 9th Street:
    • Intermittent Sutro/Oddie (half intersection closures). Detours will be posted.
    • One way for each direction along Oddie.
      • Traffic configuration change: South side closure- Thursday April 25 until May 15 (tentative date).

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com


SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

May 8 – May 31 (tentative dates)

  • One-way westbound-only traffic will be allowed on Selmi Drive at all times (24/7). Detours are provided for eastbound traffic thru McCarran Boulevard.

Accesses remain open for both businesses and residential.


STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844

  • Major construction is complete and two-way traffic has been restored.
  • Shoulder and lane closures may take place intermittently as construction cleanup occuurs.
  • On-street parking may remain closed in some areas as construction wraps up.

PYRAMID WAY AND NORTH MCCARRAN BOULEVARD FIBER CONNECTIVITY
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

This project is substantially complete.  Occasional shoulder closures may occur on Pyramid Way between Nugget Avenue and C Street for final work items.


TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Moana Lane and Baker Lane/Smith Drive (Reno)

The following traffic control will be in place at the intersection of Moana Lane, Baker Lane, and Smith Drive for traffic signal installation:

  • Intermittent lane and shoulder closures.
  • Full closure of the Smith Drive approach will occur at times. A detour will be provided.

Prater Way and 4th Street (Sparks)

The following traffic controls will be in place until the end of April at the intersection of Prater Way and 4th Street for traffic signal replacement:

  • A temporary all-way stop will be in effect at the intersection.
  • Various lane and shoulder closures.
  • All turning movements and driveways will remain open.

Delays are possible and motorists should consider an alternate route until the work is complete.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Construction is underway and will continue through June. Motorists can expect the following traffic controls:

Baring Boulevard between Sparks Boulevard and Vista Boulevard

  • Various lane and shoulder closures for fiber optic installation.
  • Lane closures (if needed) will occur Monday thru Friday, 9:00 a.m. – 3:00 p.m. daily.

Vista Boulevard between Baring boulevard and Los Altos Parkway (south)

  • Various shoulder closures for fiber optic installation.

Los Altos Parkway between Ion Drive and Sparks Boulevard

  • Various shoulder closures for fiber optic installation

STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. Traffic is shifted to the center of Steamboat Parkway between Veterans Parkway and Marketplace Drive.

May 13 to May 17

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.

SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closure on westbound Damonte Ranch Parkway between Promenade Way and Double R Boulevard, 7:00 a.m. to 7:00 p.m.
  • Single lane closure on eastbound South Meadows Parkway between Double R Boulevard and Veterans Parkway near I-580
  • Single lane closure on westbound South Meadows Parkway near Double Diamond Parkway