Pembroke Drive Capacity & Safety

PROJECT DETAILS


RTC Project No. 0217005

RTC Project Manager (PM)


Maria Paz Fernandez, P.E.


(775) 335-1861


mpazfernandez@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Nichols Consulting Engineers (NCE)

Construction Contractor: To be determined

PROJECT DESCRIPTION


Improve capacity and safety along Pembroke Drive from South McCarran Boulevard to Veterans Parkway. The project includes widening Pembroke Drive and connect existing multi-use paths on McCarran Boulevard and Veterans Parkway.

LATEST NEWS


NCE started the preliminary design investigation and aquatic resources delineation. Thirty percent plans are expected by mid-January 2024.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: Winter 2023


Final Design: End of Winter 2024


Construction: Start of Summer 2025

FINANCIAL INFORMATION


Total Project Estimate: $ 19,790,000


Funding Source: RTC Fuel Tax

Post updated on: September 29, 2023

Pembroke Drive Capacity & Safety Project Map