Traffic Signal Modifications 23-01

PROJECT DETAILS


RTC Project No. 0247011

RTC Project Manager (PM)


Sara Going, P.E.


(775) 335-1897


sgoing@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Westwood

Construction Contractor: To be determined

PROJECT DESCRIPTION


As part of RTC’s Traffic Engineering Program, Traffic Signal Modification 23-01 will implement spot improvements at 19 intersections and perform engineering evaluations for four intersections.

The project locations and scope are listed below:

Spot Improvement Locations:


1. Clearacre Lane and North McCarran Boulevard – Remove north/ south split traffic signal phasing.


2. Battle Born Way and Galletti Way – Install new signal controller cabinet and vehicle detection
system.


3. El Rancho Drive and G Street – Remove east/west split traffic signal phasing.


4. Los Altos Parkway and Galleria Parkway – Extend westbound to southbound left turn pocket.


5. Robb Drive and MaeAnne Avenue – Install new metered service with battery backup system.


6. Golden Valley Road and North Hills Boulevard – Install new metered service with battery backup system, traffic signal controller cabinet, and vehicle detection system.


7. Plumb Lane and Plumas Street – Install new metered service with battery backup system and new traffic signal controller cabinet. Modify existing vehicle detection system.


8. Ryland Street and Locust Street – Install new metered service with battery backup system and new traffic signal controller cabinet.


9. West Street and W. 4th Street – Install new traffic signal controller cabinet.


10. Sutro Street and Wedekind Road – Install new vehicle detection system.


11. South McCarran Boulevard and Greensboro Drive – Install new vehicle detection system.


12. South McCarran Boulevard and Mayberry Drive – Install new vehicle detection system.


13. West Plumb Lane and Lakeside Drive – Modify existing vehicle detection system.


14. East Plumb Lane and Kirman Avenue – Modify existing vehicle detection system.


15. Arrowcreek Parkway and Wedge Parkway – Install accessible pedestrian push buttons.


16. Mount Rose Highway and Wedge Parkway – Install battery backups system and accessible pedestrian push buttons.


17. Mount Rose Highway and Thomas Creek Road – Install battery backups system and accessible pedestrian push buttons.


18. Sun Valley Boulevard and E. 4th Avenue – Modify traffic signal heads.


19. Sun Valley Boulevard and E. 5th Avenue – Install accessible pedestrian push buttons.


Engineering Evaluations:


20. La Posada and Cordoba Boulevard – Intersection Control Evaluation


21. Nichols Boulevard and Howard Drive – Circulation Study


22. Visa Boulevard and Disc Drive – Evaluate Turn Lanes


23. Pyramid Highway and Calle De La Plata – Evaluate Turn Lanes

LATEST NEWS


The project will be advertised for construction bids in September.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: September 2022


Final Design: May 2023


Construction: Summer/Fall 2023

FINANCIAL INFORMATION


Total Project Estimate:
 $ 1,950,617


Funding Source: RTC Fuel Tax


Post updated on: August 28, 2023