Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0215007
RTC Project Manager (PM)
Bryan Byrne, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: To be determined
PROJECT DESCRIPTION
Buck Drive Circulation Project will improve the existing and future traffic flow along Buck Drive between Lemmon Drive and North Hills Boulevard. Improvements include access management implementation, road widening with traffic signal at North Hills Boulevard.
LATEST NEWS
Kimley-Horn and Associates has finalized the design and the project will go out to bid this Winter 2025. Construction is tentatively anticipated to begin in Spring 2026.
SCHEDULE
Planning: 2023
Environmental: N/A
Preliminary Design: 2024
Final Design: October 2025
Construction: Spring/Summer 2026
FINANCIAL INFORMATION
Total Project Estimate: 3,570,164
Funding Source: RTC Fuel Tax
Post updated on: October 28, 2025
Buck Drive Circulation Project Map