Status: Archived Projects
PROJECT DETAILS
RTC Project No. 0244010
RTC Project Manager (PM)
Scott Gibson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: J-U-B Engineers
Construction Contractor: Sierra Nevada Construction (SNC)
PROJECT DESCRIPTION
Corrective Maintenance is intended to address deficiencies in roads that are to poor for preventive maintenance but to good for rehabilitation or reconstruction. A variety of tools are used to cost effectively extend the life of the region’s pavements.
LATEST NEWS
The project is substantially complete.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: October 2022
Construction: October 2023
FINANCIAL INFORMATION
Total Project Estimate: $2,400,000
Funding Source: RTC Fuel Tax
Post updated on: March 26, 2024
2023 Corrective Maintenance Project Map