Status: Active Projects
PROJECT DETAILS
RTC Project No. 0211006
RTC Project Manager (PM)
Scott Gibson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project includes pedestrians, multi-modal and ADA improvements. There are also, intersection improvements at Vine Street and lighting improvements throughout the neon line corridor.
LATEST NEWS
The project has been awarded to Q&D construction with work expected to start mid-July 2025.
SCHEDULE
Planning: N/A
Environmental: To be determined
Preliminary Design: To be determined
Final Design: February 2025
Construction: April 2025
FINANCIAL INFORMATION
Total Project Estimate: $8,900,000
Funding Source: RTC Fuel Tax
Post updated on: June 24, 2025