Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0211006
RTC Project Manager (PM)
Scott Gibson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project includes pedestrians, multi-modal and ADA improvements. There are also, intersection improvements at Vine Street and lighting improvements throughout the neon line corridor.
LATEST NEWS
Wood Rodgers sixty percent design have been completed and submitted to the City of Reno and utilities for review.
SCHEDULE
Planning: N/A
Environmental: To be determined
Preliminary Design: To be determined
Final Design: February 2025
Construction: April 2025
FINANCIAL INFORMATION
Total Project Estimate: $8,900,000
Funding Source: RTC Fuel Tax
Post updated on: November 25, 2024