Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 212081
RTC Project Manager (PM)
Garrett Rodgers, P.E.
(775) 332-2139
grodgers@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: J-U-B Engineers, Inc.
Construction Contractor: To be determined
PROJECT DESCRIPTION
(1) Meadowood Mall Way between South Virginia Street and Meadowood Mall Circle, (2) Meadowood Mall Circle between South Virginia Street and Meadowood Mall Circle, and (3) Neil Way between Neil Road and Meadowood Mall Circle.
LATEST NEWS
Surveying, geotechnical investigation and preliminary engineering are in progress.
SCHEDULE
Planning: To be determined
Environmental: To be determined
Preliminary Design: Spring 2024
Final Design: Summer 2024
Construction: Spring 2025
FINANCIAL INFORMATION
Total Project Estimate: $1,769,956
Funding Source: RTC Fuel Tax
Post updated on: April 23, 2024