TRAFFIC SIGNAL FIBER 25-01

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 247014

RTC Project Manager (PM)
Austin McCoy, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Kimley-Horn and Associates, Inc.

Construction Contractor: Fibertel

PROJECT DESCRIPTION
This project will Install traffic signal fiber on:

  • Vista Boulevard between Prater Way and Baring Boulevard
  • Longley Lane between Maestro Drive and South McCarran Boulevard
  • Kietzke Lane between Fisherman’s Park and Galetti Way
  • Galetti Way between Kietzke Lane to Glendale Avenue

LATEST NEWS
The project was awarded to Fibertel. The project construction is anticipated to begin in May.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: April 2024 – September 2024
Final Design: September 2024 – January 2025
Construction: May 2025 – August 2025

FINANCIAL INFORMATION
Total Project Estimate: $3,001,483
Funding Source: RTC Fuel Tax

Post updated on: April 28, 2025

Traffic Signal Fiber 25-01 Project Map