SCHEDULE
Planning: NA
Environmental: N/A
Preliminary Design: Current to November 2022
Final Design: November 2022 to May 2023
Construction: September 2023 – Summer 2024
FINANCIAL INFORMATION
Total Project Estimate: $1,589,643.25
Funding Source: RTC Fuel Tax
Post updated on: August 29, 2024