PROJECT DESCRIPTION
This project will construct traffic fiber to improve traffic signal operations and safety on the following corridors:

  • Pyramid Way between Nugget Avenue and C Street (including the interstate 80 interchange)
  • North McCarran Boulevard between Rock Boulevard and Sullivan Lane

LATEST NEWS
Construction is nearing substantial completion.

SCHEDULE
Planning: NA
Environmental: N/A
Preliminary Design: Current to November 2022
Final Design: November 2022 to May 2023
Construction: September 2023 – Early 2024

FINANCIAL INFORMATION
Total Project Estimate:
 $1,589,643.25
Funding Source: RTC Fuel Tax


Post updated on: April 23, 2024