Status: Archived Projects
PROJECT DETAILS
RTC Project No. 512017
RTC Project Manager (PM)
Amanda Callegari, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Atkins North America
Construction Contractor: Spanish Springs Construction
PROJECT DESCRIPTION
Widening from one lane in each direction to two lanes in each direction with a center turn lane and rehabilitation of Sky Vista Parkway from Silver Lake Drive to just east of Sky Vista Parkway. Improvements include street lighting, eight-foot sidewalks and five-foot bike lanes on both sides of the roadway.
LATEST NEWS
Construction on Sky Vista Widening project has reached substantial completion.
SCHEDULE
Planning: Complete
Environmental: N/A
Preliminary Design: Complete
Final Design: March 2022
Construction: August 2022 to October 2023
FINANCIAL INFORMATION
Total Project Estimate: $17,700,000
Funding Source: Regional Road Impact Fee (RRIF)
Post updated on: March 22, 2024
Sky Vista Widening Rehabilitation Project Map