2023 PREVENTIVE MAINTENANCE PROGRAM

Status: Archived Projects

PROJECT DETAILS
RTC Project No. 0243017

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: Lumos and Associates

Construction Contractor:  Sierra Nevada Construction (SNC)

PROJECT DESCRIPTION
Preventive Maintenance is keeping good roads good by using regular inexpensive surface treatments, slow the aging process and dramatically extend the life of the region’s pavements. Treatments used include crack sealing, patching and slurry seals.

2023 Preventive Maintenance list of streets

2023 Preventive Maintenance Project Map 

LATEST NEWS
The project is substantially complete.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: October 2022
Construction: May 2023

FINANCIAL INFORMATION
Total Project Estimate: $12,748,702
Funding Source: RTC Fuel Tax


Post updated on:  March 26, 2024