SPARKS BOULEVARD CAPACITY IMPROVEMENT (GREG STREET TO BARING BOULEVARD)

Status: Active Projects

PROJECT DETAILS
RTC Project No. 227001

RTC Project Manager (PM)
Garrett Rodgers, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: ATKINS North America

Construction Contractor: Granite Construction Company (South Phase), Granite Construction Company (North Phase)

PROJECT DESCRIPTION
The project will increase safety, add roadway capacity, and improve bicycle and pedestrian facilities by widening Sparks Boulevard between I-80 westbound ramps and Baring Boulevard, with additional roadway improvements between Baring Boulevard and Shadow Lane. Please visit SparksBLVDproject.com to learn more about the project.

LATEST NEWS
Construction started September 15, 2025. Initial items of work include tree removals, utility relocations and structural work within the North Truckee drain. The community is encouraged to stay informed of the project.

Construction is complete for the southern segment (Phase 1) of the project, between Greg Street and I-80.

SCHEDULE
Planning: N/A
Environmental: Spring 2020 – Spring 2021
Preliminary Design: Spring 2021 – Fall 2021
Final Design: Fall 2021 – Fall 2024
Construction: Fall 2025 – Summer 2027

FINANCIAL INFORMATION
Total Project Estimate: $86,430,917.1
Funding Source: Federal

Post updated on: November 25, 2025

Sparks Boulevard Capacity Improvement (Greg Street to Baring Boulevard) Project Map