Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0247012
RTC Project Manager (PM)
Sara Going, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: To be determined
PROJECT DESCRIPTION
The project is part of RTC’s Traffic Engineering Program and includes analysis and improvements to spot locations regionwide:
- (Reno) North McCarran Boulevard and 7th Street – Evaluate traffic, bus, and pedestrian circulation and safety improvements near the intersection of McCarran Boulevard and 7th Street.
- (Reno) South Virginia Street and Center Street – Pedestrian safety improvements at the roundabout.
- (Reno) Vassar Street and Harvard Way – Modify intersection pavement markings to improve northbound to westbound turning movements for RTC buses.
- (Sparks) Rock Boulevard and C Street – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) North McCarran Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) Rock Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) Proctor R. Hug High School Circulation Study – Review pedestrian and circulation issues surrounding the high school for short and long term improvements.
- (Sparks) Outlets at Legends / Lincoln Way Circulation Study – Review traffic circulation and conflicts along Lincoln Way within the Outlets at Legends development.
LATEST NEWS
The project has been advertised for construction bids and work will begin in November 2024.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Winter 2024
Final Design: Spring/Summer 2024
Construction: Fall 2024
FINANCIAL INFORMATION
Total Project Estimate: $1,750, 000
Funding Source: RTC Fuel Tax
Post updated on: September 27, 2024
Traffic Signal Modification 24-01 Project Map