Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0217006
RTC Project Manager (PM)
Jessica Dover, P.E.
(775) 335-1831
jdover@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: To be determined
PROJECT DESCRIPTION
The project will modify the roundabout at Geiger Grade Road and Veterans Parkway to improve operations and increase capacity of the intersection.
LATEST NEWS
RTC is working with the consultant to complete preliminary design efforts on the project. Preliminary design is anticipated in Spring 2024.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2024
Final Design: Summer 2024
Construction: Fall/Winter 2024
FINANCIAL INFORMATION
Total Project Estimate: $2,750,000
Funding Source: RTC Fuel Tax
Post updated on: April 23, 2024
Veterans Roundabout Modifications Project Map