2024 CORRECTIVE MAINTENANCE SOMERSETT

Status: Active Projects

PROJECT DETAILS
RTC Project No. 244011

RTC Project Manager (PM)
Scott Gibson, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Wood Rodgers

Construction Contractor: SNC

PROJECT DESCRIPTION
This project consists of resurfacing Somersett Parkway from Mae Anne Avenue to Del Webb Parkway.

Somersett Phase 1 Map

Phase 1: Mid August to early September – Lower Utilities

Somersett Phase 2 Map

Phase 2A: Early September to late September – Mill and pave westbound lanes

Somersett Phase 3 Map

Phase 2B: Late September to mid October – Mill and pave eastbound lanes

Somersett Phase 4 Map

Phase 3: Mid October to early November – Raise utilities, striping, and signage

LATEST NEWS
SNC is completing utility raising activities and has begun striping operations. Substantial completion is expected by mid November.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: March 2024
Construction: August 2024

FINANCIAL INFORMATION
Total Project Estimate: $7,200,000
Funding Source: RTC Fuel Tax

Post updated on: October 28, 2024