2024 PREVENTIVE MAINTENANCE PROGRAM

Status: Active Projects

PROJECT DETAILS
RTC Project No. 243018

RTC Project Manager (PM)
Jessica Dover, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Lumos and Associates, Inc.

Construction Contractor: Sierra Nevada Construction, Inc. (SNC)

PROJECT DESCRIPTION
Crack sealing, patching and microsurfacing of regional roads at various locations.

2024 Preventive Maintenance list of streets

2024 Preventive Maintenance Project Map

LATEST NEWS
Construction is in progress; slurry, striping/thermo ongoing at various locations.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: March 2024
Construction: May 2024

FINANCIAL INFORMATION
Total Project Estimate: $7,482,440
Funding Source: RTC Fuel Tax

Post updated on: September 27, 2024