Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 247013
RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project will make the following improvements at the Vista Boulevard and Disc Drive intersection:
- Construct a southbound Vista Boulevard to westbound Disc Drive dedicated right-turn lane
- Construct a westbound Disc Drive to southbound Vista Boulevard dedicated left-turn lane
- Extend the eastbound Disc Drive to northbound Vista Boulevard left-turn lane
LATEST NEWS
The project design has been completed and right of way has been acquired. Final utility coordination is in progress. The construction contract is expected to bid in February 2025 with construction beginning in Spring 2025.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer/Fall 2024
Construction: Spring 2025
FINANCIAL INFORMATION
Total Project Estimate: $2,605,155.00
Funding Source: RTC Fuel Tax
Post updated on: December 27, 2024
Vista Boulevard/Disc Drive Intersection Improvements Project Map