PROJECT DESCRIPTION
This project will make the following improvements at the Vista Boulevard and Disc Drive intersection:

  • Construct a southbound Vista Boulevard to westbound Disc Drive dedicated right-turn lane
  • Construct a westbound Disc Drive to southbound Vista Boulevard dedicated left-turn lane
  • Extend the eastbound Disc Drive to northbound Vista Boulevard left-turn lane

LATEST NEWS
Alternatives analysis was conducted. Preferred alternatives have been selected and are advancing in design.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer/Fall 2024
Construction: Spring 2025

FINANCIAL INFORMATION
Total Project Estimate: $1,750,000.00
Funding Source: RTC Fuel Tax