PROJECT DETAILS
RTC Project No. 247013
RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: Sierra Nevada Construction
PROJECT DESCRIPTION
This project will make the following improvements at the Vista Boulevard and Disc Drive intersection:
- Construct a southbound Vista Boulevard to westbound Disc Drive dedicated right-turn lane
- Construct a westbound Disc Drive to southbound Vista Boulevard dedicated left-turn lane
- Extend the eastbound Disc Drive to northbound Vista Boulevard left-turn lane
LATEST NEWS
Initial exploratory work is expected to begin in May, with major reconstruction work beginning mid Summer.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer/Fall 2024
Construction: Spring 2025
FINANCIAL INFORMATION
Total Project Estimate: $2,476,550.00
Funding Source: RTC Fuel Tax
Post updated on: April 28, 2025