VISTA BOULEVARD/DISC DRIVE INTERSECTION IMPROVEMENT

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 247013

RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1

RTC Engineering Department
(775) 348-0171

Design Firm: Wood Rodgers

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project will make the following improvements at the Vista Boulevard and Disc Drive intersection:

  • Construct a southbound Vista Boulevard to westbound Disc Drive dedicated right-turn lane
  • Construct a westbound Disc Drive to southbound Vista Boulevard dedicated left-turn lane
  • Extend the eastbound Disc Drive to northbound Vista Boulevard left-turn lane

LATEST NEWS
Project design has reached the fifty percent milestone. Analysis and acquisition of necessary right of way is now underway.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer/Fall 2024
Construction: Spring 2025

FINANCIAL INFORMATION
Total Project Estimate: $1,750,000.00
Funding Source: RTC Fuel Tax

Post updated on: June 27, 2024

Vista Boulevard/Disc Drive Intersection Improvements Project Map