December 27, 2024

ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Construction is substantially completed


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

December 23 – December 27

  • Construction is substantially completed
  • Intermittent lane shifts for punch item list work:
    • Two lanes in each direction will remain open along South Virginia Street between 7:00am and 9:00am and 4:00 pm to 6:00pm (day work).
    • At least one lane will be open on South Virginia Street starting at 6:00pm everyday until 7:00am the next day (night work).
  • Traffic Signal at I-580 northbound Exit 29 off-ramp expected to be operating after the holidays.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

No work this week, project will be shutdown for the holiday week.

December 23 – December 27

  • No restrictions


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

Construction is substantially complete. Isolated work may continue at project sites as the contractor completes punch list items.


TRAFFIC SIGNAL MODIFICATION 24-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

Construction at Midtown sites is substantially complete. Isolated work may continue as the contractor completes punch list items through the end of December.