SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
This project is substantially complete. Some localized traffic control may occur as the contractor works through punch list items through early December.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape maintenance work.
- Between US 395 and Sutro Street in Reno:
- Lane closures for privacy wall work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
December 2 – December 6
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Week of December 2 (weather dependent):
- Crews are expected to work during the day.
- Finish raising utilities, miscellaneous asphalt and sidewalk concrete work and landscaping.
- Traffic Signal at I-580 northbound Exit 29 off-ramp expected to be active by mid-December.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
This week crews will be striping and landscaping.
December 2 – December 6
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Damonte Ranch Parkway and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is substantially complete.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
December 2 – December 6
No work or traffic control is scheduled for this week.
TRAFFIC SIGNAL MODIFICATION 24-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
December 2 – December 6
Work will resume in Midtown Reno on December 2.
Monday, Thursday, and Friday:
Virginia Street will be closed in the southbound direction from St. Lawrence Avenue to Taylor Street during daytime working hours. A signed vehicular detour route will be provided via Forest Street. Pedestrians should follow all sidewalk detour signage near work zones.
Tuesday:
Wells Avenue will be closed from S. Virginia Street to Casazza Drive. Motorists and pedestrians should follow the signed detours provided.
Wednesday:
Isolated sidewalk and shoulders will be closed at the intersection of Virginia Street and Center Street. Pedestrian detours will be provided.