TRAFFIC SIGNAL MODIFICATIONS 24-01

Project Overview

Label Value
Status Archived Projects
Project Details 0247012
RTC Project Manager (PM) Ashley Hurlbut, P.E.
RTC Engineering Department (775) 348-0171
Design Firm Kimley-Horn and Associates, Inc.
Construction Contractor Sierra Nevada Construction, Inc.

Project Description

The project is part of RTC’s Traffic Engineering Program and includes analysis and improvements to spot locations regionwide:

  • (Reno) North McCarran Boulevard and 7th Street – Evaluate traffic, bus, and pedestrian circulation and safety improvements near the intersection of McCarran Boulevard and 7th Street.
  • (Reno) South Virginia Street and Center Street – Pedestrian safety improvements at the roundabout.
  • (Reno) Vassar Street and Harvard Way – Modify intersection pavement markings to improve northbound to westbound turning movements for RTC buses.
  • (Sparks) Rock Boulevard and C Street – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
  • (Sparks) North McCarran Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
  • (Sparks) Rock Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
  • (Sparks) Proctor R. Hug High School Circulation Study – Review pedestrian and circulation issues surrounding the high school for short and long term improvements.
  • (Sparks) Outlets at Legends / Lincoln Way Circulation Study – Review traffic circulation and conflicts along Lincoln Way within the Outlets at Legends development.

Latest News

Construction of the project was substantially completed September 2025.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Winter 2024
Final Design: Spring/Summer 2024
Construction: Summer 2025

Financial Information

Total Project Estimate: $3,243, 976
Funding Source: RTC Fuel Tax