PROJECT DETAILS
RTC Project No. 0212076
RTC Project Manager (PM)
Judy Tortelli, P.E.
(775) 335-1824
RTC Engineering Department
(775) 348-0171
Design Firm: Nichols Consulting Engineers
Construction Contractor: To be determined
PROJECT DESCRIPTION
Rehabilitation of First Street from Sierra Street to Virginia Street and reconstruction of the First Street/Sierra Street intersection. This portion of work was removed from the Reno Consolidated 20-01 Project due to increased scope to upgrade the traffic signal system to current city standards.
Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, and other incidentals necessary to construct the project. The project includes replacement of the traffic signal system at the First Street/Sierra Street intersection.
LATEST NEWS
Invitation for bids advertised on August 16, 2023. Construction is scheduled to begin in October 2023. Depending on the weather, paving work may be completed in Spring 2024.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: August 2022 – January 2023
Final Design: January – April 2023
Construction: Fall 2023
FINANCIAL INFORMATION
Total Project Estimate: $ 1,350,500
Funding Source: RTC Fuel Tax
Post updated on: August 25, 2023