PROJECT DESCRIPTION
This project will rehabilitate the pavement on Stanford Way from Greg Street to Glendale Avenue. Other improvements will include new sidewalk, drainage upgrades, and upgrades for ADA accessibility.
LATEST NEWS
Final design is underway.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2022 to Spring 2023
Final Design: Spring 2023 to Fall 2023
Construction: Spring 2024
FINANCIAL INFORMATION
Total Project Estimate: $3,424,571
Funding Source: RTC Fuel Tax
Post updated on: October 5, 2023