PROJECT DETAILS
RTC Project No. 0217007
RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
(775) 335-1880
RTC Engineering Department
(775) 348-0171
Design Firm: HDR Engineering
Construction Contractor: To be determined
PROJECT DESCRIPTION
Installation of traffic fiber and other intelligent transportation systems (ITS) along Veterans Parkway between Steamboat Parkway and Long Meadow Drive.
LATEST NEWS
Design has begun on this project. Underground exploratory work will occur in the coming months.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2023 – Winter 2023
Final Design: Winter 2023 – Spring 2024
Construction: Summer 2024
FINANCIAL INFORMATION
Total Project Estimate: $2,000,000
Funding Source: RTC Fuel Tax
Post updated on: September 29, 2023