CORRECTIVE MAINTENANCE 2027

Project Overview

Label Value
Status Upcoming Projects
Project Details 214002
RTC Project Manager (PM) Garrett Rodgers, P.E.
Design Firm Eastern Sierra Engineering (ESE)
Construction Contractor To be determined

Project Description

Corrective maintenance of Plumas Street and Plumb Lane in Reno, Nevada. Plumb Lane will include full roadway width milling and paving with isolated patching, striping replacement and updates, signage replacement and updates, and concrete improvements to include pedestrian ramps and driveways. Plumas Street will include milling and paving travel lanes only, striping replacement and upgrades, signage replacement and upgrades.

Latest News

Preliminary project scoping and investigation of existing conditions is underway. Preliminary design is expected in the Spring of 2026.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2026
Final Design: Summer 2026
Construction: Spring 2027

 

Financial Information

Total Project Estimate: $8,653,223.00
Funding Source: RTC Fuel Tax