MCCARRAN BOULEVARD SAFETY AND OPERATIONAL IMPROVEMENTS

Project Overview

Label Value
Status Upcoming Projects
Project Details 0245008
RTC Project Manager (PM) Jessica Dover, P.E.
RTC Engineering Department (775) 348-0171
Design Firm Wood Rodgers
Construction Contractor To be determined

Project Description

RTC’s McCarran Boulevard Safety and Operational Improvements project is a multi-year effort that seeks to: identify segment  limits and associated scope of improvements throughout the McCarran Boulevard corridor, in alignment with established RTP transportation goals and associated performance monitoring processes, implement strategic prioritization and tracking of proposed improvements, utilize data obtained and resulting prioritization to pursue future funding opportunities; and advance two (2) segments of the corridor to final design and construction. The limits associated with these (2) segments are approximately defined as included per the RTC Street and Highway Program for Fiscal Year 2024.

Latest News

  • 30% design received for Northtowne Lane to Pyramid Way; and, Plumas Street to S. Virginia Street
  • Task Order No. 1 under the Master Services Agreement to be completed in January 2026

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2025
Final Design: Fall 2026
Construction: To be Determined

Financial Information

Total Project Estimate: $32,670,000
Funding Source: RTC Fuel Tax