PYRAMID HIGHWAY OPERATIONS IMPROVEMENTS

Project Overview

Label Value
Status Upcoming Projects
Project Details 0237002
RTC Project Manager (PM) Jessica Dover, P.E.
RTC Engineering Department (775) 348-0171
Design Firm Atkins North America Inc.
Construction Contractor To be determined

Project Description

Pyramid Highway Operations Improvements:

  • Ingenuity Avenue to Egyptian Drive

Latest News

Hundred percent design is anticipated to be complete in Spring 2026.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Summer 2025
Final Design: Winter 2025
Construction: Spring 2026

Financial Information

Total Project Estimate: 17,062,952
Funding Source: RTC Fuel Tax

To bid, click here:  https://rtcwashoe.procureware.com/login 