SIERRA STREET BRIDGE REPLACEMENT

Project Overview

Label Value
Status Upcoming Projects
Project Details 0711001
RTC Project Manager (PM) Bryan Byrne, P.E.
RTC Engineering Department (775) 348-0171
Design Firm Jacobs Engineering Group, Inc.
Construction Contractor To be determined

Project Description

The project includes removal and replacement of existing bridge that was constructed in 1937.

Latest News

The project team has successfully completed the ninety percent design milestone. Work is now shifting toward advancing the plans to a hundred percent design stage, incorporating feedback received to date and refining project details. Coordination with the construction Manager at Risk (CMAR) contractor is ongoing to support constructability reviews, cost evaluations and scheduling considerations as the design progresses.

Visit the Project Website

More information is available at SierraStreetBridge.com

Schedule

Planning: N/A
Environmental: Fall 2024 – Fall 2025
Preliminary Design: May 2023 – May 2024
Final Design: June 2024 – May 2026
Construction: Spring 2027

Financial Information

Total Project Estimate: $37,162,475
Funding Source: Federal

  • Bridge Formula Program Off-System – $3.5M (PE) and $12.5M (CON)
  • Surface Transportation Block Grant (STBG) Bridge – $10.8M (CON)

To bid, click here:  https://rtcwashoe.procureware.com/login 