TRAFFIC SIGNAL FIBER 25-01

Project Overview

Label Value
Status Active Projects
Project Details 247014
RTC Project Manager (PM) Austin McCoy, P.E.
RTC Engineering Department (775) 335-1824
Design Firm Kimley-Horn and Associates, Inc.
Construction Contractor Fibertel

Project Description

This project will Install traffic signal fiber on:

  • Vista Boulevard between Prater Way and Baring Boulevard
  • Longley Lane between Maestro Drive and South McCarran Boulevard
  • Kietzke Lane between Fisherman’s Park and Galetti Way
  • Galetti Way between Kietzke Lane to Glendale Avenue

Latest News

The project construction is ongoing and is anticipated to be complete in early 2026.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: April 2024 – September 2024
Final Design: September 2024 – January 2025
Construction: June 2025 – January 2026

Financial Information

Total Project Estimate: $2,941,609.6
Funding Source: RTC Fuel Tax