TRAFFIC SIGNAL FIBER 26-01

Project Overview

Label Value
Status Upcoming Projects
Project Details 227007
RTC Project Manager (PM) LaShonn Ford, P.E.
RTC Engineering Department (775) 332-2136
Design Firm HDR Engineering, Inc.
Construction Contractor To be determined

Project Description

The project will install conduit and fiber on Sullivan Lane from Greenbrae Drive to Victorian Avenue and El Rancho Drive from McCarran Boulevard to Prater Way in order to connect the signals to the network. Connecting the signals will increase RTC’s capabilities to manage traffic operations in the region.

Latest News

The project has been solicitated to contractors for bids. A contractor will be selected by April 2026. Construction is anticipated to begin shortly after, and be completed Summer 2026.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2025
Final Design: Fall 2025
Construction: Spring 2026 – Summer 2026

Financial Information

Total Project Estimate: $2,083,491.00
Funding Source: RTC Fuel Tax

To bid, click here:  https://rtcwashoe.procureware.com/login