TRAFFIC SIGNAL TIMING 7 PROJECT

Project Overview

Label Value
Status Active Projects
Project Details 8131036
RTC Project Manager (PM) Alex Wolfson, P.E., PTOE, RSP1
RTC Engineering Department (775) 335-1880
Design Firm Partnership between RTC, City of Reno, City of Sparks, and the UNR Center for Advanced Transportation Education and Research
Construction Contractor To be determined

Project Description

The traffic Signal Timing project is a collaborative partnership between the RTC, Cities of Reno and Sparks, and the UNR Center for Advanced Transportation Education and Research. The goal of the project is to continue the re-timing of 1/3 of the signals each year and to expand signal timing plans to include weekends, holidays and special event plans, if possible. The schedule of work for a typical corridor consists of the following:

  • Collect traffic and signal data
  • Input timings into model and evaluate existing signal timing
  • Develop new timing and implement in the field
  • Fine-tune timing, and conducting before-after studies

This project will provide signal re-timing engineering services for a 3-year cycle beginning in July, 2023, and concluding in June 2026.

Latest News

New signal timing plans have been deployed on Vista Boulevard for the morning and evening commute. Testing of new timing plans along North McCarran Boulevard are in progress. Other corridors recommended for retiming are:

  • Clear Acre Lane and Sun Valley Boulevard
  • Pyramid Way
  • South Virginia Street in the Meadowood Mall area

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: N/A
Construction: July 2023 – June 2026

Financial Information

Total Project Estimate: $1,358,800
Funding Source: RTC Fuel Tax

Project Map

Project Map