BUTCH CASSIDY DRIVE EXTENSION

Status: Upcoming Projects

Total Project Cost: $6,000,000

PROJECT DETAILS
RTC Project No. 0235001

RTC Project Manager (PM)
Kimberly Diegle, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: CA Group

Construction Contractor: To be determined

PROJECT DESCRIPTION
The RTC is planning to extend the roadway at Butch Cassidy Drive and connect to Mount Rose Highway at Thomas Creek Road. This project will provide a new two-lane road facility with associated bicycle and pedestrian improvements. Other improvements will include drainage, lighting and landscaping improvements.

LATEST NEWS
Preliminary design is underway.

SCHEDULE
Planning: Complete
Environmental: 
N/A
Preliminary Design: Fall 2024 to Spring 2025 
Final Design:  
Spring 2025 to Winter 2025/2026
Construction: 
2026

FINANCIAL INFORMATION
Total Project Estimate: $11,560,000
Funding Source:
 RTC Fuel Tax


Post updated on: November 25, 2024