LEMMON DRIVE TRAFFIC IMPROVEMENTS AND RESILIENCY

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 0217001

RTC Project Manager (PM)
Bryan Byrne, P.E.
(775) 335-1865
bbyrne@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Preliminary Design Firm: CA Group, Inc.

NEPA/Final Design Firm: To be determined

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes operational improvements along Lemmon Drive from Fleetwood Drive to Ramsey Way. Elements of this project include resilience improvements to mitigate historical flooding issues.

LATEST NEWS
The project is actively advancing in completing the necessary NEPA studies. The project team is working to address public input into the design.

Lemmon Drive – Alternatives (Level 1)
Lemmon Drive – Alternatives (Level 2)
Lemmon Drive – 30% Preliminary Plans

SCHEDULE
Planning: N/A
Environmental: 2023-2024
Preliminary Design: 2023-2024
Final Design: 2024-2025
Construction: To be determined (based on funding)

FINANCIAL INFORMATION
Total Project Estimate: $49,200,000.00
Funding Source: RTC Fuel Tax

Post updated on: April 23, 2024

Lemmon Drive Traffic Improvements and Resiliency Project Map